Skip to content

What type of bundle will be required by the COP for a remote hearing?

Physical bundles may not be regarded as safe for public health and there are obvious difficulties in providing them with the current restrictions in place. Electronic bundles should be provided in PDF format, preferably paginated, indexed and bookmarked. The bundles should only contain documents and authorities that are essential to the issues required to be decided at the remote hearing and should be filed with the court by email.

Related FAQs

Do employers still have to enrol and reenrol employees?
  • Yes, and this includes furloughed employees under the Coronavirus Job Retention Scheme.
  • Employers must continue to assess their new employees or newly eligible existing employees and enrol them where required, but can make use of the statutory postponement procedure which allows them to delay for up to three months the assessment of new employees for the purpose of enrolment (see further details here on the Pensions Regulator’s website). Declarations of compliance for new employers must still be completed in the normal way.
  • Postponement cannot be used for re-enrolment. The Regulator recommends employers use the re-enrolment date tool on the Regulator’s website to choose a date up to three months after the third anniversary of enrolment to assess staff for re-enrolment. Further information about employers’ obligations about reenrolment from the Pensions Regulator can be found here. Re-declarations of compliance for new employers must still be completed in the normal way.
Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.

Retraining and redeploying

If the business has areas requiring an increased workforce whilst others require a reduced workforce, staff can be retrained and redeployed across the organisation or even across a wider group of companies. This will not reduce the wage bill but will avoid the need for redundancies. Making fundamental changes to an employee’s role and duties will require their agreement following a fair selection and consultation process.

What challenges to planning permission does the current lockdown situation present?
  • Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
  • Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
  • Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
  • The ability to get people on site to undertake material operations

In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.

If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?