What should payroll look out for if the Government’s Coronavirus Job Retention Scheme is used?
- It is important to have a clear paper trail for any agreed reduction in salary, and hence any reduction in the amount of contributions. However, the contribution rates (as opposed to the amounts) should be the same as normal, and hence all processes and software should function as per normal and, amongst other things, remain compliant with auto-enrolment employer duties.
- However, if the period of affected contributions does not overlap precisely with the period of reduced salary, for example because of different cut-off dates, there may well be instances of non-compliance with auto-enrolment employer duties at the beginning as well as at the end of the period covered by the Coronavirus Job Retention Scheme.
- Accordingly, where an employer takes advantage of the Coronavirus Job Retention Scheme, good communication with the persons responsible for pensions administration and detailed record-keeping are essential to prevent non-compliances in the short-term and confusion in the long term.
Related FAQs
- The Pensions Regulator has published regularly-updated guidance for employers.
- It will take “a proportionate and risk-based approach towards enforcement decisions … with the aim of supporting both employers and savers”. In other words, the law remains the same, but the Regulator will show restraint in enforcement against breaches.
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.
Yes, if they are paid via PAYE. This includes agency workers engaged under umbrella companies.
The furlough should be agreed between the agency (the employer) and the worker and documented in accordance with the guidance. It is recommended that the decision to furlough is discussed with end user clients. Just like other employees, agency workers cannot perform work through or on behalf of the agency while furloughed. This includes work for the client.
For agency staff working under umbrella companies, it is for the umbrella company and the agency worker to agree on furloughing the worker.
On 25th June 2020, the Corporate Insolvency and Governance Act, among other things, introduced new restrictions on suppliers of goods and services to terminate the contract in the event that the customer enters an insolvency process. This has very important consequences for many businesses as it could expose them to greater financial risks.
Under CBILS, for the purposes of calculating the applicant’s annual turnover, approved lenders have been aggregating turnover across the whole of the private equity investor’s portfolio meaning they failed to qualify for the scheme as they were deemed to exceed the £45 million threshold.
For private equity-backed businesses, the removal of the upper limit on annual turnover criteria for CLBILS seemingly avoids the issue of turnover aggregation across investment portfolios seen with the CBILS, potentially enabling more private equity sponsor portfolio companies to be able to access the CLBILS funding.