Understanding of the extent of the Covid-19 risk to BAME colleagues is evolving – what does that mean for NHS employers?
In practice this means that any risk assessment will need to be reviewed constantly and adjusted as our understanding of the nature and level of the risk grows.
Some service-providers are instigating special Oversight Groups to keep this issue under review but engagement and consultation with those affected is critical and making sure they feel confident to raise concerns and refuse to work if they believe they are not safe.
Related FAQs
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.
A break or pause in learning can be initiated where the interruption to learning due to Covid-19 is greater than four weeks. This must be reported as a formal break in learning. In such circumstance the funding to the training provider will be suspended for the duration of the break. Previously, the rules only allowed an apprentice to initiate this break in learning but this has been expanded to give employers and training providers the right to initiate this. Training providers should continue with their monthly IRL submissions to the ESFA. During breaks in apprenticeships it is not necessary for the apprentice to comply with the minimum of 20% on the job training requirement but this will resume when the break ends.
Some employers falling into the third group of organisations described above could understandably feel aggrieved that on the first reading of the guidance they are not able to furlough employees and rely on the Government scheme. Many publicly funded organisations that are not public sector employers, receive a package of public funding with little expectation on how that funding is used or applied, other than broadly for it to be used in providing the services it is contracted to deliver. Also, several publicly funded organisations have many different income streams and the element of funding that is received from the public purse can be only an element of their operating costs.
Unfortunately there is still no clear guidance on when employers falling into the third category identified above can use the scheme. The only reference in the guidance on this states that where organisations are not “primarily funded” from the public purse and whose staff cannot be redeployed to assist with the coronavirus response, the scheme might be appropriate to be used for some staff. This seems to suggest that where an employing organisation is not wholly or mainly funded by public funding and staff cannot be redeployed to work in areas in the effort to combat coronavirus, then it would be appropriate for the employer to access the scheme.
If considering applying for grants under the scheme a sensible approach would be to look at the combined total of your public funding and payments under the scheme and make sure it will not represent more than 100% of the level of total income you would have expected to receive during this period in a non-Covid scenario.
Local Authorities are expected to maintain support to suppliers and this should be considered:
Many will have worked collaboratively with their suppliers and customers to deal with the immediate public health crisis. This will have meant offering flexibility as to contractual arrangements, whether in delivery dates, volumes of goods or services supplied, or even in the specification of what has been delivered.
If this is the case, it is important that businesses now do their legal housekeeping and make sure they have a proper record of what has been agreed. Unfortunately, our experience shows that many legal disputes arise out of amendments to contracts, typically where the parties to the contract each have a different view about what exactly they agreed to change.
We would therefore advise businesses to review any amendments that they might have agreed either verbally, by email, or otherwise, and consider whether they need to be captured in a more formal way which will make clear exactly what has been agreed to be varied, and (where appropriate) how long that variation will remain in force.
It’s also important to remember that some contracts contain provisions that set out specific requirements about how amendments are to be made. For example, they might require that amendments are made in writing (rather than verbally). These “No Oral Modification” clauses are commonly found in commercial contracts, and the courts have recently shown that they are willing to enforce them.
Failing to deal with amendments in accordance with contractual requirements could therefore have a serious impact on businesses as they recover from the disruption caused by the lockdown. If they end up in dispute with a customer or supplier, a business could find that the contract has not actually been amended in the way that they think – potentially leading to legal costs and liabilities at the worst possible time.