Skip to content

Understanding of the extent of the Covid-19 risk to BAME colleagues is evolving – what does that mean for NHS employers?

In practice this means that any risk assessment will need to be reviewed constantly and adjusted as our understanding of the nature and level of the risk grows.

Some service-providers are instigating special Oversight Groups to keep this issue under review but engagement and consultation with those affected is critical and making sure they feel confident to raise concerns and refuse to work if they believe they are not safe.

Related FAQs

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

What are the limitations of furloughing staff for publicly funded organisations?

The guidance from the Government concerning private sector organisations is very different from the guidance for public sector and organisations that receive public funding. The guidance states:

“The government expects that the scheme will not be used by many public sector organisations, as the majority of public sector employees are continuing to provide essential public services or contribute to the response to the coronavirus outbreak.

Where employers receive public funding for staff costs, and that funding is continuing, we expect employers to use that money to continue to pay staff in the usual fashion – and correspondingly not furlough them. This also applies to non-public sector employers who receive public funding for staff costs. Organisations who are receiving public funding specifically to provide services necessary to respond to Covid-19 are not expected to furlough staff.”

This guidance isn’t particularly clear but it appears that there is a recognition that there are different types of organisations which could be caught by this:

  1. Organisations who will be required to provide frontline services during the Covid-19 response. It is interpreted that NHS organisations such as NHS Trusts will fall firmly into this category. Employees of such organisations are expected not to be furloughed and to continue to work and be paid their normal salary in the usual way.
  2. Organisations who receive public funding to provide services to respond to the Covid-19 crisis. These organisations are not expected to furlough their staff. The type of organisation that would fit into this category are those that have been commissioned to developing breathing apparatus or testing kits to meet the needs of the healthcare sector during the peak of the pandemic.
  3. Organisations who receive public funds for staff costs to operate services. Employers are expected to continue to pay staff if the money to pay them is publicly funded. It is strongly inferred that this is irrespective of whether such staff have any work to perform. The type of organisation that is likely to fall into this category are GP practices, charities and private sector companies that have won contracts with the public sector.
My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

Can I enact a rent suspension clause in my commercial lease?

Most rent suspension clauses in commercial property leases are unlikely to come to the assistance of the tenant. These clauses normally apply only where the premises has suffered substantial physical damage and are, as a consequence, incapable of being occupied, used or accessed. The coronavirus pandemic does not involve any physical damage to a property, loss from the crisis will be purely financial. Such losses then will not be covered by the landlord’s buildings insurance policy in a way that will allow a tenant to claim rent suspension.

Should I continue to carry out housing inspections during the coronavirus outbreak?

As the pandemic progresses, more and more people will be forced to self-isolate and, inevitably, both tenants and staff will be affected. Put plans in place to mitigate the impact that this may have, particularly regarding staff shortages. The most important focus here should be communication.

The Covid-19 outbreak will affect the pace of everyday life and delays will be expected. Rather than allowing the pandemic to take over completely, it is important to maintain open communication with tenants as much as possible and inform them of any front-facing challenges that you may face.

The Protocol does envisage that delays may occur and allows for some degree of flexibility. Whilst all efforts should be made to conduct inspections where practical and possible, it should be expected by all parties that timescales will be extended during this crisis. It is fundamental, however, that all changes made to standard practice are communicated and explained to tenants to manage expectations.

Similar flexibility should be afforded to tenants. As households are required to isolate it will not always be possible to gain access to properties as would usually be expected and required. Likewise, vulnerable people will wish to protect themselves and their families and may refuse access on this basis. During this period, a degree of understanding must be exercised and concessions made.

Inspections may be delayed if anyone in the household has  symptoms. A questionnaire should be prepared for those visiting properties to assess so far as possible the risk; Personal Protective Equipment should be issued to those visiting, and government guidelines followed.