How is an establishment defined?
The definition of a relevant establishment is a question of fact for an Employment Tribunal. Guidance from case law says that ‘establishment’ should be interpreted very broadly (so as to avoid employers escaping the need to collectively consult), and may consist of:
- A distinct entity
- With a certain degree of permanence and stability
- Which is assigned to perform one or more tasks
- Which has a workforce, technical means and a certain organisational structure to allow it to do so
However, there is no need for it to have the following:
- Legal, economic, financial, administrative or technological autonomy
- A management which can independently effect collective redundancies
- Geographical separation from the other units and facilities of the undertaking
Related FAQs
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
On 13 March 2020 the Secretary of State for Housing, Communities and Local Government issued a Written Statement in respect of delivery restrictions.
In this respect, many supermarkets, food retailers and distribution centres in England operate under planning restrictions (conditions and/or obligations) which limit the time and number of deliveries from lorries and other delivery vehicles which can take place particularly at night primarily to protect the residential amenity of nearby residential property.
Key points in the Statement include;
- Given the exceptional challenges facing the UK from the coronavirus, it is vital that deliveries of food, sanitary and other essential products over the coming weeks can be made as quickly and safely as possible, minimising disruption to the supply chains. The likely pressures on driver capacity mean additional flexibility is needed so that retailers can accept deliveries throughout the day and night where necessary.
- That planning enforcement is discretionary and that local planning authorities should act proportionately in responding to suspected breaches of planning control.
- That local planning authorities should not seek to undertake planning enforcement action which would result in unnecessarily restricting deliveries of food and other essential deliveries during this period having regard to their legal obligations.
The Statement acknowledges that the increased frequency of deliveries particularly at night could have a temporary impact on residents. It therefore concludes that the Government will review the need for the flexibility outlined in the Statement after the pressure from the coronavirus has reduced and that it is the intention to withdraw it once the immediate urgency has subsided.
A link to the Written Statement is below.
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.
Yes, but as a last resort. In summary, the law requires employers:
- to assess the workplace risks posed to new or expectant mothers or their babies;
- to alter the employee’s working conditions or hours of work to avoid any significant risk to them;
- where it is not reasonable to alter working conditions or hours, or would not avoid the risk, to offer suitable alternative work on terms that are not “substantially less favourable”;
- where suitable alternative work is not available, or the employee reasonably refuses it, the employer should consider whether it is appropriate to suspend the employee on full pay.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.