Can I have legal documents signed and witnessed?
Solicitors can be authorised to sign contracts for their clients – a signed letter of authority should be scanned and sent to avoid posting potentially contaminated documents.
Solicitors should exchange supplemental agreements on behalf of their clients to agree to postpone exchange and completion dates if it has been agreed to push these back.
The Law Society advises that electronic signatures be used as much as possible for contracts, to avoid possible contamination. However, the Land Registry confirms that the legal transfer document cannot be validly executed with an electronic signature. Solicitors should agree a completion undertaking that the original transfer document will be sent when received and after the restrictions have been lifted.
The Land Registry’s latest guidance https://www.gov.uk/guidance/coronavirus-covid-19-impact-on-hm-land-registrys-services published on 14 May states:
We accept deeds that have been signed using the ‘Mercury signing approach’.
For land registration purposes, a signature page will need to be signed in pen and witnessed in person (not by a video call). The signature will then need to be captured, with a scanner or a camera, to produce a PDF, JPEG or other suitable copy of the signed signature page. Each party sends a single email to their conveyancer to which is attached the final agreed copy of the document and the copy of the signed signature page.
Solicitors should be willing to adopt this procedure for completing transactions to enable them to be registered by the Land Registry.
The execution of a transfer is a deed and must be witnessed. Members of the family can witness signatures so long as they are not also a party to the document. A witness will be more credible if they are 18 or over, but this is not a legal requirement. The legal requirement is for the witness “to be present” when the document is signed. It would be possible for a witness to be on the other side of the room or the other side of a window, and validly witness the execution of a deed. The witness does need to take precautions to avoid possible contamination from the document.
A statutory declaration does not need to be witnessed but must be administered by a solicitor or commissioner for oaths. There is no legally prescribed process for this, and there is nothing to suggest that this could not be validly done via a video telephone call if the signature on the declaration can clearly be seen by the person commissioning the oath when the oath is made.
Related FAQs
The golden thread requirements will be retrospective, so will apply to existing buildings as well as new build. This is part of the reason for the Building Safety Regulator’s ‘get to know your building’ guidance referred to in the talk, with the link in the Powerpoint presentation. While the details of the golden thread requirement are still to be confirmed, now is a good time to start to gather as much information as can be obtained about existing buildings as possible in preparation. The Government guidance anticipates that the Principal Accountable Person will be responsible for developing and coordinating the golden thread for existing buildings.
The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.
With time and resource precious commodities, focus should be given to documenting:
- The key changes to your PFI requirements
- The temporary nature of the measures
- The requirement for best efforts on behalf of the PFI Contractor
- The importance of continued health and safety measures at all times
Mortuaries are a sui generis use, unless ancillary to some other use of land, a hospital for example.
Sui generis uses are not within any Use Class. Consequently planning permission is required for the:
- Change in the use to a sui generis use
- Subsequently for the change in the use to an alternative use, whether that be another sui generis use or a use within a Use Class
Acknowledging the above, if the scale of the use is above de minimis, planning permission is likely to be required to change the use of a warehouse or factory unit into a temporary mortuary.
Should planning control be breached, a local planning authority must decide whether to take enforcement action or not. That enforcement is discretionary was recently reiterated in a Ministerial Statement issued on 13 March 2020 a link to which is below.
Depending on the form of the enforcement action, there could be a right of appeal.
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
On 2 April 2020, the Government issued guidance relating to Private Finance Initiatives and PF2 Projects. The guidance, which is to be enforced with immediate effect (currently due to stay in place until 30 June 2020), is one of several guidance notes issued to date.
A link to the guidance is set out below:
Key messages to contracting authorities
- PFI contractors should very much consider themselves as being part of the public sector response to the current pandemic
- Covid-19 is not regarded as, and is not to be classified as a force majeure event
- PFI contractors must ensure that contingency plans are up to date and have been reviewed and discussed with contracting authorities to enable the continuity of full services to respond to the pandemic and maintain vital public services
- Contracting authorities should work closely with PFI contractors to use all available options to maintain public services during the emergency period
- Local arrangements should be made where PFI contractors can’t deliver the agreed requirements and performance standards
- “Best efforts” should be made by all parties for the continuation of service provision