Can I be fined for failing to take steps to try to ensure that my staff comply with the requirements to self-isolate?
Yes.
An employer which is aware that a worker or agency worker is or ought to be self-isolating, should not knowingly allow that worker or agency worker to leave the place that they are self-isolating in (“the designated place”). To do so without reasonable excuse would amount to an offence which could result in the employer being issued with a fixed penalty notice.
The value of the fixed penalty varies depending on if it is the first or subsequent fixed penalty notice to be issued:
| First fixed penalty notice | £1,000 |
| Second fixed penalty notice | £2,000 |
| Third fixed penalty notice | £4,000 |
| Fourth, and any subsequent fixed penalty notice | £10,000 |
Related FAQs
Safeguarding issues are relatively uncommon, however, if they do occur, the normal safeguarding procedure of the organisation should be followed.
Whilst it is acknowledged that doctors may be working in unfamiliar circumstances or surroundings, or in clinical areas outside their usual practice. Doctors should consider the best course of action to take in these circumstances by utilising the following:
- What is within their knowledge and skills
- What support other members of the healthcare team could offer
- What will be best for the individual patient given available options
- The protection and needs of all patients they have a responsibility towards
- Minimising the risk of transmission and protecting their health.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.
If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.
It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.
Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.
Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.
As above, employees must not leave their home unless they have a ‘reasonable excuse’.