Skip to content

Can I be fined for failing to take steps to try to ensure that my staff comply with the requirements to self-isolate?

Yes.

An employer which is aware that a worker or agency worker is or ought to be self-isolating, should not knowingly allow that worker or agency worker to leave the place that they are self-isolating in (“the designated place”).  To do so without reasonable excuse would amount to an offence which could result in the employer being issued with a fixed penalty notice.

The value of the fixed penalty varies depending on if it is the first or subsequent fixed penalty notice to be issued:

First fixed penalty notice £1,000
Second fixed penalty notice £2,000
Third fixed penalty notice £4,000
Fourth, and any subsequent fixed penalty notice £10,000

Related FAQs

How do I implement temporary contractual arrangements?

The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.

With time and resource precious commodities, focus should be given to documenting:

  • The key changes to your PFI requirements
  • The temporary nature of the measures
  • The requirement for best efforts on behalf of the PFI Contractor
  • The importance of continued health and safety measures at all times
How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

Can I apply a Force Majeure clause?

If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.

The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.

You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:

  • Has a force majeure event actually arisen?
  • What notification process do you have to follow to rely on the provision?
  • What mitigation steps do you have to take?
  • What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
What if we are a charity in Scotland Wales or Northern Ireland?

Because they all have devolved governments, when there are changes to spending levels in England, the Government makes adjustments to the amount of public expenditure allotted to Scotland, Wales and Northern Ireland.  In this case £60 million will be made available for all of the devolved administrations as a result of the £370 million funding allocated to charities in England. This is broken down as follows:

  • £30 million for the Scottish Government
  • £20 million for Welsh Government
  • £10 million for the Northern Ireland Executive

There may be further allocations, dependent on the final projects funded, through the £360 million direct grant pot.

Are there any other useful resources about apprenticeships during the coronavirus outbreak?

On 6 April 2020 the Government published further guidance to clarify the position with apprentices during the Covid-19 outbreak. The full guidance is available from here https://www.gov.uk/government/publications/coronavirus-covid-19-apprenticeship-programme-response/coronavirus-covid-19-guidance-for-apprentices-employers-training-providers-end-point-assessment-organisations-and-external-quality-assurance-pro

The guidance includes details of the measures implemented by the Education and Skills Funding Agency (ESFA) in order to provide flexibility in delivering apprenticeships in current circumstances. This includes breaks in learnings, delayed end point assessments and alternative arrangements for end point assessments. These measures apply immediately and until further notice.

There are a number of FAQs within the Government guidance which deal with common queries. The guidance contains some technical provisions and we recommend that you take advice if you are furloughing or making apprentices redundant. If you have any additional queries on the practicalities of implementing the ESFA measures please get in touch.

Further guidance changes to apprenticeships due to coronavirus can be found here.