Skip to content

Will there be further measures for self-employed announced?

The Government assured parity for the self-employed but it has since accepted that this would be difficult to achieve. The Association of Independent Professionals and the Self-Employed (IPSE) has worked closely with the Government on implementing the current self-employment income support scheme. IPSE has confirmed that it will continue to work on helping to extend measures to all freelancers in need as a result of Covid-19.

The Government announced an extension to the Self-Employment Income Support Scheme from 1 November 2020.

 

Related FAQs

Can I ask for relief from KPIs or service credits under a contract with a public sector body if the Covid-19 outbreak means that I am having difficulty in performing it?

The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.

The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.

The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:

  • Amending the contract requirements
  • Varying timings of deliveries
  • Relaxing KPIs or service levels
  • Extending time for performance (e.g. revising a contract delivery plan), and/or
  • Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).

These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.

A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.

If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.

 

 

Court proceedings haven’t yet been issued – what should I do?

Parties still need to comply with the various Protocols that apply and will be expected to exchange information in the usual way. Court proceedings can be issued electronically.

What other options are there to reduce employment costs?

If you don’t want to make redundancies, or if you can’t reduce employee resource, either in a particular department or across the workforce as a whole, then you need to think about alternatives to redundancy.

Equally, you may want to flex the resource you have available to you – without making drastic changes.  For example you may want to consider:

  • unpaid leave and sabbaticals
  • retraining and redeploying
  • forcing annual leave
  • flexible working
  • capability issues
  • lay off
  • short time working
  • reductions in salary
  • reductions in working hours
  • changing to shift working
What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases

The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:

  • The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
  • How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
  • Whether the definition of higher risk buildings is correct, or will require some refinement.

The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.