Will holiday entitlement continue to accrue for a period of furlough?
The guidance has confirmed that all remaining employment rights and terms continue while an employee is furloughed. Holiday will continue to accrue during furlough however you may reach agreement with employees on reducing entitlement provided that it does not fall below the statutory minimum of 5.6 weeks per year.
Related FAQs
The amount an insurer charges for providing cover is a critical aspect of the underwriting process. The premium must be sufficient to cover expected claims but must also take into account the possibility that the insurer will have to access its capital reserve –it is risk assessment based and the greater the risk, the higher the premium. Historically, insurers of high-rise buildings would have only had to prepare for a loss caused by damage to just a few flats within a building. That is because the design and construction of that building, with the right materials and fire safety provisions in place, should have limited the spread of fire and allowed the damage to be contained –or at least make this an extremely low risk. Now we know that many buildings have been designed, built and signed off in a regulatory system that an independent Government review has found was not fit for purpose. Premiums will reduce overtime but will be dependent upon the perceived level of risk reducing as the regulatory regime, BSA and BSR become more established.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
The government released further clarification on the Coronavirus Job Retention Scheme on 4 April. The wording referred to concerning public sector organisations and organisations receiving public funding remains the same.
The revised guidance does provide a helpful insight into how HMRC will deal with applications made to it for assistance under the scheme. It appears that there won’t be a particularly forensic approach adopted by HMRC. The guidance says you can furlough staff if you cannot maintain your current workforce because your operations have been severely affected by coronavirus.
It goes on to say that all employers are eligible to claim under the scheme and the government recognises different businesses/organisations will face different impacts from coronavirus. The need to demonstrate the impact of coronavirus on your business/organisation is not one of the criteria businesses/organisations are going to need to satisfy, so the government does not appear to intend to set a specific test to determine if a business/organisation is “severely impacted by coronavirus”. It is hoped that this should provide additional comfort to publicly funded organisations facing significant restrictions to their operations during the Covid-19 crisis.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Because they all have devolved governments, when there are changes to spending levels in England, the Government makes adjustments to the amount of public expenditure allotted to Scotland, Wales and Northern Ireland. In this case £60 million will be made available for all of the devolved administrations as a result of the £370 million funding allocated to charities in England. This is broken down as follows:
- £30 million for the Scottish Government
- £20 million for Welsh Government
- £10 million for the Northern Ireland Executive
There may be further allocations, dependent on the final projects funded, through the £360 million direct grant pot.