Will councillors still be able to vote if they can’t meet in person?
Local government legislation formerly stipulated that councillors must be physically present to vote and this requirement has already led to the widespread cancellation of Council meetings. There is a limit to what can be achieved under the chair’s emergency powers and delegation to officers.
The Government has now legislated to allow for remote voting until 7 May 2021. The secondary legislation required was issued in draft on 2 April and has been in force since Saturday 4 April.
The legislation allows for committee meetings to go ahead where members and any members of the public attending remotely can all times “hear (and where possible see) and be heard (and where possible be seen) by the other members in attendance”.
It remains to be seen how many local authorities take up the opportunity to hold a virtual committee meeting. Concern has been expressed that the demographic of local councillors may mean that members have difficulty with the technological mechanisms for holding such meetings. However, the message from the Secretary of State is clear that wherever possible, the planning system should keep moving in these current times.
Related FAQs
Crucially the phrase “force majeure” has no specific meaning in English law. As a result, there is scope for complex legal argument, including as to whether the effects of the coronavirus outbreak can amount to force majeure in the first place. If the coronavirus crisis deepens, force majeure provisions could become relevant in the following ways:
- suppliers to your business might seek to invoke force majeure
- you may need to invoke force majeure under your own contracts
Each of these will need careful analysis of the relevant contract against the applicable factual background. Unfortunately, the position is unlikely to be clear cut.
As the coronavirus outbreak continues to develop, we have seen many countries begin to implement emergency procedures and legislation in an attempt to control the spread of the disease.
These have included bans on gatherings and public events, closures of shops, bars, restaurants and public spaces, and full lockdowns which restrict all but key workers to their homes except in certain limited circumstances.
This has a direct impact on businesses and their ability to operate. So what happens if a contract becomes impossible to perform because of emergency legislation?
For example:
- If you are a hospitality business, you have agreed to host an event, and gatherings are prohibited
- If you are a manufacturer or service provider, and your staff are required to remain at home, making performance of the contract impossible
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:
- Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
- Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
- Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
- Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
- Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
- Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
- Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
- Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
- Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!
In general. there is often a stick or twist decision. If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful. Conversely, withholding payments from the contractor may make insolvency a self-fulfilling prophecy. The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.