Skip to content

Which agreements will qualify for exemption?

There are four criteria which must be satisfied if an agreement is to be considered exempt:

  • It must improve production or distribution, or promoting technical or economic progress – the guidance suggests that cooperation ensuring essential goods and services can be made available to the public, or an important sub-set of the public such as key workers, will satisfy this criterion.
  • It must allow consumers a fair share of the resulting benefit – the guidance suggests this will be the case where the action prevents or reduces shortages.
  • It must not impose on the undertakings concerned restrictions which are not indispensable to the attainment of the above benefits – the guidance suggests this will be the case where the cooperation is the only reasonable option due to the urgency of the crisis and where the cooperation is temporary in nature.
  • It must not afford the undertakings concerned the possibility of eliminating competition – therefore the parties must endeavour to retain competition in respect of the products (in particular price competition).

Related FAQs

What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

How do you prevent MHFA from handling situations that are for qualified individuals such as their GP or EAP?

The MHFA training makes this clear, it should be made clear in the MHFA role specification and procedures and discussed during regular MHFA peer support and MHFA surgery sessions. It is important to ensure that where an Employee Assistance Programme is in place, all MHFAs have details of that scheme available so they are able to instantly share details of the scheme with those who require support. If in doubt due to serious concerns then using 999 or Samaritans is an option.

What challenges to planning permission does the current lockdown situation present?
  • Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
  • Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
  • Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
  • The ability to get people on site to undertake material operations

In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.

If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.

What if a contractor is deemed to be employed?

The fee payer that pays the fee to the contractor’s PSC for the services (end user client or agency) will be responsible for operating PAYE and deducting NIC’s. The fee payer must also pay employer NIC’s and where applicable the apprenticeship levy so there will be additional costs involved in the event of a change to employed status for tax purposes.

If the assessment concludes that the contractor is self-employed, the PSC can continue to be paid gross.

What are the current planning restrictions on supermarkets, food retailers and distribution centres concerning deliveries?

On 13 March 2020 the Secretary of State for Housing, Communities and Local Government issued a Written Statement in respect of delivery restrictions.

In this respect, many supermarkets, food retailers and distribution centres in England operate under planning restrictions (conditions and/or obligations) which limit the time and number of deliveries from lorries and other delivery vehicles which can take place particularly at night primarily to protect the residential amenity of nearby residential property.

Key points in the Statement include;

  • Given the exceptional challenges facing the UK from the coronavirus, it is vital that deliveries of food, sanitary and other essential products over the coming weeks can be made as quickly and safely as possible, minimising disruption to the supply chains. The likely pressures on driver capacity mean additional flexibility is needed so that retailers can accept deliveries throughout the day and night where necessary.
  • That planning enforcement is discretionary and that local planning authorities should act proportionately in responding to suspected breaches of planning control.
  • That local planning authorities should not seek to undertake planning enforcement action which would result in unnecessarily restricting deliveries of food and other essential deliveries during this period having regard to their legal obligations.

The Statement acknowledges that the increased frequency of deliveries particularly at night could have a temporary impact on residents. It therefore concludes that the Government will review the need for the flexibility outlined in the Statement after the pressure from the coronavirus has reduced and that it is the intention to withdraw it once the immediate urgency has subsided.

A link to the Written Statement is below.

https://www.parliament.uk/business/publications/written-questions-answers-statements/written-statement/Commons/2020-03-13/HCWS159/