When should I apply to extend the period allowed to file accounts?
The application has to be made before the date on which the accounts should have been filed, so this process can’t be used if you are already late. If you don’t make the application before your filing deadline, then a fine will automatically be generated if your accounts are filed late. Whilst you could appeal against such a fine on the grounds that the delay was caused by coronavirus issues, this is likely to be a much more time consuming and uncertain process that applying in advance.
It does not appear that the process applies to Confirmation Statements or other returns.
Related FAQs
It is absolutely critical to creating a safe workplace and to making workers feel secure.
This could include floor markings every 2m (as we’ve seen in grocery stores), stopping or limiting/staggering access to communal or common areas such as toilets and kitchens, rearranging workstations to maintain a 2 metre distance or, where this is not possible (for example in manufacturing facilities or production lines), erecting physical barriers and avoiding face to face working, encouraging the use of stairs and discouraging lift-use, designing a one-way system for entry and exit and looking at aircon/heating systems to see if any modifications are possible to prevent the spread of airborne particles. If you can increase ventilation in your workplace, it will help reduce risk.
The government has published detailed social distancing guidance for workplaces across sectors including manufacturing, retail, offices, construction and transport; it has also promised to continue to add to this.
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
If suppliers still wish to terminate the contract, they must contact the directors or the officeholder dealing with the insolvency process and obtain their approval to terminate the contract – which, of course, might not be given.
If the continued obligation under the contract to supply goods/services to the customer would place the supplier in financial hardship the supplier can apply to court for permission to terminate the contract. This will involve time and legal expense.
You should have in place a dispute resolution procedure that sets out the appeal process or contractors or the agency as appropriate. You must respond to an appeal within 45 days.
If the status determination is disputed you should consider the contractor or agency’s reasons objections. You must consider if the original determination is to be maintained and give reasons for this. Or a new determination with reasons can be provided if appropriate.
Records of disputed determinations and the outcome of any appeal should be kept.
The CMA is particularly concerned about certain activities, its guidance highlights:
- Exchange of commercially sensitive information where this is not necessary in response to the crisis
- Collaboration which unfairly excludes third parties
- Abuse of a dominant position (including a dominant position held as a result of the crisis) – particularly to charge excessive prices
- Seeking to maintain prices or prevent reductions in prices
- Cooperation going beyond what is necessary to respond to the crisis in the interests of consumers