When does Flexible Furlough start?
The Flexible Furlough Scheme was introduced from 1 July 2020 and is due to come to an end on 30 September 2021.
Related FAQs
No. This bill relates to corporate insolvencies only. Should you require any advice as to personal insolvency situations, please contact our team.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
After 25 March 2020, and until 30 September 2020, a landlord can only start possession proceedings against a tenant if they have served 3 months’ notice upon the tenant – irrespective of any grounds relied upon.
On 27 March 2020, the Court introduced new rules to put all possession proceedings (except against trespassers) on hold until 25 June 2020 – it means that the Court cannot make an order for possession or any other order that would cause someone to be evicted during that time.
These rules do not just apply to tenants who have fallen into rent arrears.
On 5 June 2020, the Government announced that this stay would be extended further until 23 August 2020.
This means that you can issue new possession proceedings (provided you have complied with the new temporary rules in relation to notice periods, if the notice was served since 25 March 2020) and you can continue with existing possession proceedings.
However, any progress you may be able to make in dealing with those proceedings is likely to be very limited – the Court will allow you to comply with directions orders that have already been made but non-compliance will not be punished (at least for the time being).
These rules, and the latest announcements, are in keeping with the Government’s expectation that landlords show compassion towards affected tenants and that all parties will work together to establish a suitable repayment plan to allow tenants to repay the arrears at an affordable rate.
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
To respond to the crisis businesses might need to exchange information to a greater extent than they would usually. They might need to discuss capacity and to coordinate supply chains (both upstream and downstream). They might need to purchase or sell jointly to ensure vital supplies are maintained. In general agreements or collaboration which:
- Avoid a shortage, or ensure security, of supply
- Ensure a fair distribution of scarce products
- Continue essential services
- Provide new services such as food delivery to vulnerable consumers