What will be the impact of the proposals on suppliers?
The change in the law has the potential to place much greater financial risks on suppliers, making it more difficult to exit a contract with a customer of doubtful solvency. This will place increased emphasis on appropriate financial due diligence and credit checking before entering into supply contracts.
In addition to the obvious issues around financial risk, suppliers will also need to think carefully about how their contracts are drafted. For example, any form of right that is drafted so as to be triggered on customer insolvency will clearly be problematic. These could include:
- Retention of Title provisions, which are commonly drafted so that the right to enter premises and retake possession of the goods is triggered on insolvency;
- Provisions for brand protection, which seek to control how goods are dealt with on termination of the contract.
This is potentially a very significant development for many businesses. We would strongly recommend specialist advice be obtained so that:
- businesses understand the potential increased risks faced; and
- where possible, contracts are updated so that appropriate protections are maintained.
Related FAQs
The CMA sees only limited circumstances in which a full refund would not be given. The CMA accepts that where public health measures prevent a business from providing a service or the consumer from receiving it, the business may be able to deduct a contribution to the costs it has already incurred in relation to the specific contract in question.
This view reflects a relatively complex area of law under which parties are released from obligations under a contract if performance of that contract becomes impossible or illegal. This is called “frustration” of the contract. Under a law passed during World War II, a party to a contract that is frustrated who has incurred expenses is permitted, if the court thinks fit, to retain an amount up to the value of those expenses out of any money they have been paid by the other party.
The CMA’s view, however, is that this will not happen often, and that deductions from deposits will be limited.
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
If it is not possible to find work for the employee to do at home, you do have the option of putting the employee on furlough.
CBILS is made available through the British Business Bank’s 40+ accredited lenders and partners, which are listed on their website (https://www.british-business-bank.co.uk/ourpartners/coronavirus-business-interruption-loan-scheme-cbils/accredited-lenders/).
Businesses should initially approach their own lender and only consider other lenders if they are unable to access the finance they need. Note, not every accredited lender can provide every type of finance listed.
Some banks/lenders are not included in the list of accredited lenders which appears to mean that they cannot provide support through the Scheme. We understand from the British Business Bank that further lenders are applying to be accredited but that this may take a little time to process. If the provider of your senior debt is not on the accredited list you should consider approaching the bank which provides your day to day account banking services.
If you wish or need to access the Scheme via an alternative funder the process may take longer as usual on-boarding and KYC processes will need to be undertaken.