What technology is being used by the COP for remote hearings?
Interestingly, there is currently no ‘single’ technology to be used by the judiciary within the protocol. The court and parties must choose from a selection of possible IT platforms or audio/telephone hearing (further details available in the guidance e.g. Skype for Business, Microsoft Teams, Zoom etc.) The particular platform must be agreed at the outset of each case and then specified in the case management order. The guidance issued also sets out the basic principles which apply when conducting remote hearings.
Related FAQs
Under CBILS, for the purposes of calculating the applicant’s annual turnover, approved lenders have been aggregating turnover across the whole of the private equity investor’s portfolio meaning they failed to qualify for the scheme as they were deemed to exceed the £45 million threshold.
For private equity-backed businesses, the removal of the upper limit on annual turnover criteria for CLBILS seemingly avoids the issue of turnover aggregation across investment portfolios seen with the CBILS, potentially enabling more private equity sponsor portfolio companies to be able to access the CLBILS funding.
- On admission to hospital, all adults should be assessed for frailty, irrespective of their age and Covid-19 status. Regard should be had to any comorbidities and underlying health conditions.
- If a patient is identified as potentially having Covid-19, the UK Government guidance on infection prevention and control measures should be followed.
- If Covid-19 is then diagnosed in someone who is not isolated from admission or presentation, the UK Government guidance on actions required when a case was not diagnosed on admission should be followed.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
The Government’s Corporate Insolvency and Governance Act introduces amendments to the current rules for companies on holding meetings, to address the difficulties companies are facing due to the Covid-19 pandemic.
The new provisions apply to meetings held between 26 March 2020 and 30 September 2020 (referred to as the “Relevant Period”). Subsequent regulations by the Government can be used to shorten this period or extend by up to 3 months but not past 5 April 2021.
The provisions will have retrospective effect, so meetings that were held after 26 March 2020 that may not have met the usual legal requirements due to lockdown, will be validated under these new provisions. These provisions under the Act make amends to relevant legislation and override a company’s articles of association.
For general meetings and certain other meetings of companies, the Act states that:
- The meeting need not be held in any particular place;
- The meeting may be held, and any votes may be cast, by electronic means or other means;
- The meeting may be held without anyone being in the same place
- Persons attending the meeting no longer have the following rights: the right to attend in person, the right to participate in the meeting other than by voting, or the right to vote by particular means.
The aim of these changes is to facilitate virtual meetings, and remove the need for a physical venue.
Where a company was required to hold its AGM between 26 March and 30 September 2020, it can be held at any time before 30 September 2020. The Secretary of State has the power to make regulations to further extend the deadline.
You will be eligible if you are a self-employed individual or a member of a partnership and you:
- have trading profits of up to £50,000
- earn the majority of your income from self-employment
- have submitted a Tax Return for 2019
- have traded in the tax year 2019/20
- are trading when you apply for a grant, or would be except for Covid-19
- intend to continue to trade in the tax year 2020/2021
- have lost trading/partnership profits due to Covid-19