Skip to content

What should businesses do now?

Many will have worked collaboratively with their suppliers and customers to deal with the immediate public health crisis. This will have meant offering flexibility as to contractual arrangements, whether in delivery dates, volumes of goods or services supplied, or even in the specification of what has been delivered.

If this is the case, it is important that businesses now do their legal housekeeping and make sure they have a proper record of what has been agreed. Unfortunately, our experience shows that many legal disputes arise out of amendments to contracts, typically where the parties to the contract each have a different view about what exactly they agreed to change.

We would therefore advise businesses to review any amendments that they might have agreed either verbally, by email, or otherwise, and consider whether they need to be captured in a more formal way which will make clear exactly what has been agreed to be varied, and (where appropriate) how long that variation will remain in force.

It’s also important to remember that some contracts contain provisions that set out specific requirements about how amendments are to be made. For example, they might require that amendments are made in writing (rather than verbally). These “No Oral Modification” clauses are commonly found in commercial contracts, and the courts have recently shown that they are willing to enforce them.

Failing to deal with amendments in accordance with contractual requirements could therefore have a serious impact on businesses as they recover from the disruption caused by the lockdown. If they end up in dispute with a customer or supplier, a business could find that the contract has not actually been amended in the way that they think – potentially leading to legal costs and liabilities at the worst possible time.

Related FAQs

What should I do if I think this is relevant to my contracts?

It would be prudent to take legal advice early in relation to any issue you foresee in performing a contract. This will allow you to:

  • Ensure that initial contact with your counterparty is framed in the correct way
  • Ensure that any variations are fully documented so that both parties are fully protected
When will I receive a grant under this scheme?

The Chancellor confirmed that payments under the scheme would not be available immediately.

What happens if a patient is admitted to critical care during the pandemic?
  • On admission to critical care, the risks, benefits and likely outcomes of the different treatment options should be discussed with patients, families and carers so they can make informed decisions about their treatment wherever possible.
  • A member of the critical care team should be involved in these discussions whenever the patient or team needs advice about critical care to make decisions about treatment.
My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

Can we require employees to have their temperatures taken on the way in to work, and is this something we should be doing?

If such testing is regarded as a “reasonably practicable step” which has been identified as an appropriate control following a risk assessment then it is something you can do.

Although you can’t physically force someone to have something intrusive done, this is very likely to be a reasonable management instruction and therefore if someone refuses to have this done as a condition of entry into the work place then disciplinary action may follow.

Where this is something that is required of employees, employers should be letting their staff know that this is one of a number of measures that are being introduced into the workplace for their own safety. If the employer can explain, in advance of the return, why temperature checks need to be taken, what the consequences of the results will be- i.e. will they be sent home if over a certain temperature, whether this data will be stored (and if the sole purpose is to determine whether or not they are fit to attend work on a particular day then why are they being stored), and the fact that temperature checks are a requirement of entry to company premises for everyone, then there shouldn’t be significant resistance to this measure.

Large scale temperature checks have in some businesses become part of the “new normal” working environment.