Skip to content

What should be included in genuinely self-employed contractor terms?

If you consider the factors used to determine status you can include the following terms that are more in line with a self-employed relationship:

  • The right to provide a substitute of the contractor’s choice in the event the individual is not able to perform the services;
  • The ability to work for other businesses as long as doing so will not affect the services to be provided by the contractor;
  • The contractor should have sufficient control over how, when and where (if possible) they provide the services;
  • A degree of financial risk can be included for unsatisfactory work or failing to complete a project or task

We have terms that cover all of these points that can be tailored to your needs. The consultancy agreement is included in our IR35 toolkit.

Related FAQs

What is defined as a redundancy?

It is where the need for a role at a specific site, or the number of people performing a role, has ceased or diminished or the site closes down.

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

How do I avoid disputes and approach extensions of time and claims for additional payment with my Employer or Supplier?

The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here

The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.

The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.

Can we require employees to have their temperatures taken on the way in to work, and is this something we should be doing?

If such testing is regarded as a “reasonably practicable step” which has been identified as an appropriate control following a risk assessment then it is something you can do.

Although you can’t physically force someone to have something intrusive done, this is very likely to be a reasonable management instruction and therefore if someone refuses to have this done as a condition of entry into the work place then disciplinary action may follow.

Where this is something that is required of employees, employers should be letting their staff know that this is one of a number of measures that are being introduced into the workplace for their own safety. If the employer can explain, in advance of the return, why temperature checks need to be taken, what the consequences of the results will be- i.e. will they be sent home if over a certain temperature, whether this data will be stored (and if the sole purpose is to determine whether or not they are fit to attend work on a particular day then why are they being stored), and the fact that temperature checks are a requirement of entry to company premises for everyone, then there shouldn’t be significant resistance to this measure.

Large scale temperature checks have in some businesses become part of the “new normal” working environment.

Is the Land Registry functioning?

Yes. The Land Registry published a new service update on 14 May, here:

https://www.gov.uk/guidance/coronavirus-covid-19-impact-on-hm-land-registrys-service

Importantly, the Land Registry will process registrations where documents have been executed using the Mercury signing approach:

For land registration purposes, a signature page will need to be signed in pen and witnessed in person (not by a video call). The signature will then need to be captured, with a scanner or a camera, to produce a PDF, JPEG or other suitable copy of the signed signature page. Each party sends a single email to their conveyancer to which is attached the final agreed copy of the document and the copy of the signed signature page.

To summarise some further points:

  • Most information enquiries are experiencing minimal delays
  • Registrations of new titles, such as on sales of part or new leases, and applications to update existing titles, are experiencing more significant delays but can be expedited via the expedite service
  • Cancellation dates for replying to requisitions are extended until further notice
  • Access to free documents on the land registry portal has been extended to 90 days from completion of the transaction
  • Identity requirements have been relaxed. The Land Registry will now raise a requisition for identity documents, and not cancel applications
  • Requests for extensions to a notice or objection period will be granted if lawfully possible
  • Land charges searches can be submitted electronically with PDF documents