What should be included in genuinely self-employed contractor terms?
If you consider the factors used to determine status you can include the following terms that are more in line with a self-employed relationship:
- The right to provide a substitute of the contractor’s choice in the event the individual is not able to perform the services;
- The ability to work for other businesses as long as doing so will not affect the services to be provided by the contractor;
- The contractor should have sufficient control over how, when and where (if possible) they provide the services;
- A degree of financial risk can be included for unsatisfactory work or failing to complete a project or task
We have terms that cover all of these points that can be tailored to your needs. The consultancy agreement is included in our IR35 toolkit.
Related FAQs
Conduct risk assessments! Your RA must cover every foreseeable risk arising from a return to the workplace, including the impact of reduced staff levels and any operational/administrative changes necessary to ensure social distancing.
Appropriate steps should be taken to manage and mitigate identified risks. Where this is not possible, businesses need to decide whether certain activities are necessary for the business to operate or if they can be temporarily put on hold.
Keep a close eye on the comprehensive Government guidance: https://www.gov.uk/guidance/working-safely-during-coronavirus-covid-19
In particular focus on social distancing and workplace health measures. This guidance will evolve over time and you will need to be sure that your organisation is sticking to it AND reviewing and updating its risk assessment.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
Office holders who provide services under an intermediary (such as a service company consultancy agreement) and whose services relate to the office held, would fall under the IR35 regime and must be assessed accordingly.
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
On 4 May 2020, the Government launched the Bounce Back Loan Scheme (BBLS), which is intended to cut red tape to enable smaller businesses to access finance quickly during the coronavirus outbreak.
The scheme helps small and medium-sized businesses to borrow between £2,000 and up to 25% of their turnover. The maximum loan available is £50,000.
The government guarantees 100% of the loan and there are no any fees or interest to pay for the first 12 months. After 12 months the interest rate will be 2.5% a year.
The length of the loan is 6 years, but it can be repaid early without penalty. No repayments will be due during the first 12 months.
Under the scheme, lenders are not permitted to take any form of personal guarantee or take recovery action over a borrower’s personal assets (such as their main home or personal vehicle).
Businesses can apply for a BBLS loan if it:
- is based in the UK
- was established before 1 March 2020, and
- has been adversely impacted by the coronavirus.
Any business regarded as being a business in difficulty on 31 December 2019 will need to confirm that it is complying with additional state aid restrictions.
Businesses from any sector can apply, except the following:
- banks, insurers and reinsurers (but not insurance brokers)
- public-sector bodies, and
- state-funded primary and secondary schools.
Businesses already claiming under the following schemes cannot apply although it is possible to convert an existing loan under such schemes into BBLS:
- Coronavirus Business Interruption Loan Scheme (CBILS)
- Coronavirus Large Business Interruption Loan Scheme (CLBILS)
- COVID-19 Corporate Financing Facility.
There are 11 lenders participating in the scheme including many of the main retail banks, which are listed on the British Business Bank’s website (www.british-business-bank.co.uk/ourpartners/coronavirus-business-interruption-loan-schemes/bounce-back-loans/for-businesses-and-advisors/). Applicants are directed to approach a suitable lender via the lender’s website. If an applicant is declined by a lender, they can apply to other lenders in the scheme.
The lender will ask applicants to fill in a short online application form and self-declare that they are eligible. All lending decisions remain fully delegated to the accredited lenders.