What records do I need to keep for Flexible Furlough?
You will need to keep a copy of the written agreement for a period of 5 years. If the hours of work change from that which you initially agree, you are likely to need something new in writing to cover each separate arrangement.
You should also keep records of how many hours your employees work and how many hours they are furloughed (i.e. not working). You must keep these records for 6 years, together with a record of the amount claimed, your claim reference number and your calculations.
Related FAQs
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.
That will depend on the terms of your facility and the stance taken by your bank.
Banking facilities often place obligations on businesses to stick to certain financial criteria. For example, an obligation to keep turnover or profit above certain levels or a commitment to keep the bank’s exposure within an agreed percentage of the value of the company’s assets (known as loan to value ratio).
The consequences of breaching those covenants will depend on the terms of your facility, but normally this amounts to an event of default. Events of default can result in the loan (or whatever form the facility takes) becoming repayable and could give the bank certain powers to take action to recover the money that they are owed.
Whether the bank will take action during these unprecedented times is another matter, particularly given the extent of support being offered to businesses via mainstream lenders and the political desire to keep viable businesses up and running. Lenders themselves will no doubt wish to remain supportive where possible. The underlying performance of the business (and whether but for the effects of Covid-19 it would have been in a healthy financial position), the relationship you have with the bank and your history with them will no doubt be relevant to the approach taken by the bank. However, early engagement with your bank (as well as other key stakeholders in the business) will be important.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
In recognition of the problems that the current situation is causing, the UK IPO classed the 24th March and all subsequent days as “interrupted days” which means that deadlines that fall within this period will be extended until the UK IPO declares that the interrupted days have ceased. As lockdown has begun to be eased, the IPO has now reviewed its position and has confirmed that the “interrupted days” period will come to an end on the 29 July 2020. This means that Thursday 30 July 2020 will be the first normal day of operation, therefore all “interrupted days” deadlines will expire on this day. Similarly, if your deadline falls after the period of interruption ends, this deadline will not be automatically extended.
The IPO is conscious that many businesses may still be in challenging positions when the period of “interrupted days” end. They will endeavour to continue to provide flexibility and support to assist businesses with their applications. They hope to temporarily remove fees for requests for extensions of deadlines, and will give further updates when this fee exemption is in place.
The IPO continues to encourage applicants to meet original deadlines where they are able. As their offices are closed, the UK IPO is not currently processing paper forms (i.e. hard copy) and faxes. However, they are processing forms which have been submitted electronically, or via email and have made a new email address available for the submission of forms.
Intellectual Property Offices covering other territories have made their own announcements about the extension of deadlines. The EUIPO’s period of extension of deadlines came to an end on the 18th May. However, they have published a Guidance Note and accompanying webinar on the EUIPO website, detailing options for parties who may struggle to meet deadlines and remedies for those who may have missed deadlines.