Skip to content

What other financial support is there for businesses?

 Aside from the CBILS Scheme, the Government have, or are in the process of, implementing several different schemes to support businesses financially through the Covid-19 outbreak.

Related FAQs

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases

The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:

  • The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
  • How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
  • Whether the definition of higher risk buildings is correct, or will require some refinement.

The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.

What guidance has the Government given in relation to contracts in relation to Covid-19?

On 7 May the Government published guidance on how contracting parties can act responsibly in order to assist the effort to deal with Covid-19. The guidance seeks to persuade contracting parties to act reasonably and recognise the impact of Covid-19 on contractual counterparties. This will continue to be relevant as business begins to emerge from lockdown.

What are the standard holiday rules?

Under usual rules, workers are entitled to a minimum of 28 days holiday including bank holidays, each year. Except in limited circumstances, it cannot be carried between leave years meaning that workers lose their holiday if they do not take it.

The government passed emergency legislation relaxing the carry-over of the 20 days leave entitlement provided under EU law. Where it is not reasonably practicable for an employee to take leave in the relevant leave year as a result of the effects of the coronavirus then they could be entitled to carry over the untaken leave into the next year.

What are the data protection implications of holding Covid-19 health data?

The ICO is providing new guidance to organisations regarding data protection and coronavirus, which can be accessed here: https://ico.org.uk/for-organisations/data-protection-and-coronavirus/

Information about the Covid-19 health status of individuals is special category data under the GDPR. This means it is high risk which has implications for how you use it, store it and keep it secure.

You will already hold health data about your employees as this is necessary to provide a safe, accessible place to work and to make reasonable adjustments to the workplace. You now need to make sure that the information you gather about your employees, visitors to your sites, customers and suppliers about Covid-19 is processed in accordance with data protection laws.