Skip to content

What other financial support is there for businesses?

 Aside from the CBILS Scheme, the Government have, or are in the process of, implementing several different schemes to support businesses financially through the Covid-19 outbreak.

Related FAQs

What do I do if my visa is due to expire but I can't travel?

If your visa has expired or will do before you are able to safely leave the UK, you can apply for “Exceptional Indemnity” by contacting the Coronavirus Immigration Team. You will need to provide evidence as to why you cannot leave, which could include a positive Covid-19 test or evidence of being unable to make travel arrangements to leave the UK in time.

You should note that “Exceptional Indemnity” does not extend your leave, but temporarily protects you from adverse action being made against you as result of overstaying your visa.

How has the law changed?

In part in response to the Covid-19 pandemic, legislation was passed by the government earlier this year which sought to assist companies to trade through the current economic climate. Included within the measures is a degree of protection from compulsory winding up.

The Corporate Insolvency and Governance Act 2020 (The Act), was laid before parliament on 20 May, and became law on 26 June. It is important creditors are aware of what changes have been implemented and the potential and impact which it may have upon debt recovery action you may be considering or have already commenced.

The main part of the Act affecting creditors is the temporary restriction on presentation of winding up petitions and the factors that the Court has to take into account when deciding whether to wind up a company.

On Thursday 24 September 2020 the government passed a further statutory instrument which extended the operation of these restrictions. As a result, the measures which were due to expire on Wednesday 30 September 2020 have now been extended until 31 December 2020.

A key point to note is that the Act has retrospective effect so any pending petitions presented after 27 April will be affected, along with any winding up orders made after that date.

The Act has introduced the following restrictions:

  • A petition cannot be presented by a creditor during the period of 27 April 2020 and 31 December 2020 unless the creditor has reasonable grounds to believe that (a) coronavirus has not had a financial effect on the debtor, or (b) the debtor would have been unable to pay its debts even if coronavirus had not had a financial effect on the debtor;
  • A petition cannot be presented after 27 April 2020 if it is based on a unsatisfied statutory demand served between 1 March 2020 until 31 December 2020;
  • When deciding whether to make a winding up order the Court will need to be satisfied that the grounds giving rise to the petition would have arisen even if Covid-19 did not have a financial effect on the debtor;
  • All winding up orders made between the 27 April and 31 December will automatically be void (that is, of no legal effect) unless the Court would have made the winding up order if the new law was in force at the time the order was made.
What are the additional costs for the end user if the contractor is deemed employed?

The immediate impact is accounting for payroll purposes for the additional cost of 13.8% employers NIC’s and 0.5% apprenticeship levy on top of the payment to the contactor’s PSC.

Secondary NIC’s cannot be recovered from payments due to employees and the same applies under the new IR35 regime. However, new terms can be agreed with reduced level of fees to reflect this additional cost.

Flexible working

Many employees require flexible working now more than ever. That could be reduced hours, working from home, reduced days, etc. Be careful to act fairly when considering these requests as they can be a discrimination claim in the waiting.

A flexible working request is a request for a permanent change to the contract of employment however to encourage a greater take up during this difficult time, you can agree this on a temporary basis.

Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.