What options do I have if my employee, who can work from home, is struggling to do so because they have young children at home who need “teaching” and supervision?
This is likely to be a common situation and employers and employees are going to have to take a pragmatic approach. You could enter into a temporary flexible working arrangement perhaps agreeing to vary working hours/days or reducing targets or agree to use some annual leave.
Employees could ask to take a period of unpaid leave, asserting their right to time off to care for a dependant but the lack of pay is likely to be unappealing.
Alternatively employees who are unable to work because they have caring responsibilities as a result of COVID-19, which includes childcare responsibilities, can be furloughed.
Related FAQs
The Vice President of the COP, Mr Justice Hayden, has issued guidance to assist parties during this challenging time.
The latest guidance with all relevant updates on developments is available on the judiciary website here.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:
- The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
- How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
- Whether the definition of higher risk buildings is correct, or will require some refinement.
The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.
Where a lender requires a EWS1 as part of the mortgage requirements for a flat this will apply regardless of its tenure and will therefore apply to applicable RTB properties. It may also be required in order to obtain a valuation for the disposal notices and issues in obtaining it could cause problems in serving this within relevant deadlines required by legislation.
Unfortunately, losses caused by pandemics are not often covered expressly under standard policies, as the risk has been difficult for insurers to price and understand.
Even where additional cover in respect of notifiable diseases has been purchased, it typically will not include Covid-19 within the range of diseases covered by the policy. If the policy includes a list of notifiable diseases, and which does not include Covid-19, it is very unlikely that cover will be available for pandemic-relates losses.
The most common types of covers that could be afforded by insurance policies for coronavirus-related losses and liabilities are traditional business interruption insurance, contingent business interruption insurance, liability insurance, as well as cancellation and abandonment insurance.