Skip to content

What measures can be taken without notification to the European Commission?

There have always been ways for public bodies to assist without being required to notify these for approval. These continue to be available during the financial crisis, and are likely to be increasingly useful for measures which need to be introduced quickly. The measures include:

Those where it is possible to conclude that there is no effect on trade between Member States – for example, measures which are likely to have only a limited local effect. The European Commission has concluded, for example, that measures to assist locally-focused cultural activity can be assumed to have no effect on inter-State trade. 

Those where it is possible to conclude that the State is acting in a way consistent with a commercial operator (the so-called Market Economy Operator Principle) – particular care will need to be taken in the context of current economic conditions to ensure that it can reasonably be asserted that a commercial operator would act in the same way as the public body.

Measures under the General Block Exemption Regulation – this legislation allows various types of aid, or aid schemes, to be employed.

Examples include aid for SMEs, aid for research and development, aid for local infrastructure and aid to ports and airports.

De Minimis Measures – Member States are permitted to grant small amounts of aid to undertakings over three fiscal years (the current year and the previous two years). This allows undertakings to receive up to €200,000 (or €500,000 where they are providing public services).

Related FAQs

What should I do if contractor insolvency occurs?

In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:

  • Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
  • Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
  • Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
  • Ensure that any further payments to the contractor are stopped pending a more detailed review
  • Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession

In addition, there are also a number of further actions which the employer should consider in the slightly longer term:

  • Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
  • Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
  • Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
  • Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
  • Consider whether direct payment to subcontractors is possible or desirable
  • Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
How does this protect businesses entering into an insolvency process?

The Act is intended to facilitate the rescue of businesses that are in financial difficulty by preventing suppliers from invoking certain termination clauses under a supply contract, and therefore maintaining supply of goods and services to the business whilst plans to save the business can be considered.

Supply contracts often contain a clause enabling them to terminate the contract, or take other steps such as requiring payment in advance,  in the event that the customer enters an insolvency procedure.

This new Act removes any such contractual right by dis-applying any clause that allows the supplier to terminate the contract, or take any other step, due to the customer entering an insolvency process.

Suppliers are also prevented from demanding payment for pre-insolvency debts owed by the customer as a condition of continued supply.

Additionally, where the supplier had a contractual right to terminate the contract due to an event occurring before the customer went into the insolvency process (whether or not linked to payment issues), the supplier loses this right for the duration of the insolvency process.

Should you rely upon Statutory Demands issued after 1 March to present a Winding Up petition?

No. No action need be taken in relation to the demand but we would advise against presentation of a petition based upon any Statutory Demand issued between 1 March 2020 and the end of the restrictions. As you may be aware, with Winding Up there is no requirement to issue a Statutory Demand notice before proceeding so this is unlikely to create too many issues – click here to see whether you should issue petitions on other grounds.

There is nothing to prevent statutory demands being served at this time. However, there may be limited benefit as it cannot form the basis of a future winding up petition.

Do the usual publicity requirements for planning applications still apply?

The Government has introduced new regulations, which took effect on 14 May 2020, to relax the publicity requirements in respect of planning applications.

Planning applications are usually required to be publicised by way of site notices and local newspaper notices and applications are to be made available for public inspection. The Government has recognised that these actions may not always be possible in accordance with social distancing guidelines and in order that Councils do not delay applications as a result of an inability to comply with the publicity requirements, the Government has relaxed the requirements.

A Local Planning Authority is now required to “take reasonable steps” to publicise a planning application, which may be through use of online newspapers, social media, or other electronic measures. What is considered reasonable will depend upon the circumstances of an individual application and will be proportionate to the scale and impact of the development. A large development that has previously generated significant interest will require more steps to bring the application to the attention of all of those with an interest than a householder application. The guidance emphasises the role of the publicity requirements, namely to enable those with an interest to make representations and to effectively participate in the decision making process and therefore community engagement remains key. It is recommended that the officer’s report refers to the steps taken where a Council has relied upon the temporary publicity arrangements.

The requirement to make planning applications available for public inspection has also been temporarily suspended providing that the applications are available for online inspection. In reality most LPAs already provide such an online facility. Where individuals are unable to access an application online LPAs should make alternative arrangements, for example providing information over the phone or providing a hard copy set of documents by post.

The regulations however only amend the statutory publicity requirements. In addition to these, all LPAs are required to have a Statement of Community Involvement which may provide for additional publicity requirements and the LPA will be bound by these regardless of the temporary relaxation of any statutory requirements. Where a Statement of Community Involvement does go beyond the statutory requirements, the Government guidance suggests that LPAs update these to ensure that local communities can continue to be consulted in the current climate.

The regulations are currently due to expire on 31 December 2020.

Can an employee still do training when on Flexible Furlough?

Employees on Flexible Furlough can engage in training during hours which you record your employee as being on furlough, as long as in undertaking the training the employee does not provide services to, or generate revenue for, or on behalf of their organisation or a linked or associated organisation.

Where training is undertaken by furloughed employees during hours which you record your employee as being on furlough, at the request of their employer, they are entitled to be paid at least their appropriate national minimum wage for this time.