What is the risk if I insist that my employees have the vaccine?
If you do not have a justifiable reason for insisting that your employees have the vaccine (see FAQ above) your employee could resign and bring a claim of constructive unfair dismissal if they have more than 2 years’ continuous employment. This would be on the basis that you have breached trust and confidence.
If the vaccine includes pig gelatine (as many do), and the employee refuses on religious or because they are vegan, you may face a claim for discrimination under the Equality Act 2010.
Related FAQs
Potentially, yes. If someone refuses to follow the health and safety measures that have been put in place to protect them, colleagues and possibly their customers, including (where appropriate) the use of PPE then this is a disciplinary issue and should be dealt with as such. Repeated failure to comply with the requirement to follow these measures, or a one off significant failure, may be sufficient to justify dismissal, depending on the circumstances.
This is likely to be a common situation and employers and employees are going to have to take a pragmatic approach. You could enter into a temporary flexible working arrangement perhaps agreeing to vary working hours/days or reducing targets or agree to use some annual leave.
Employees could ask to take a period of unpaid leave, asserting their right to time off to care for a dependant but the lack of pay is likely to be unappealing.
Alternatively employees who are unable to work because they have caring responsibilities as a result of COVID-19, which includes childcare responsibilities, can be furloughed.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
You must exercise reasonable care in assessing status and making a status determination, considering what the position would be if the contractor was engaged directly by the end user client instead of via a PSC.
Status is usually determined by looking a number of factors and how they apply to the contractor’s working arrangements. This is a difficult exercise that is usually carried out by employment and tax lawyers and it is full of grey areas. We have a toolkit that can help you navigate this process which Paul will tell you more about at the end of the session.
The key factors used to determine status are:
- Control:
- How much control does the end user client have over the contractor in terms of working arrangements (hours, place of work) and how the work is carried out? Or is the individual contractor able to determine how and when they work and without direct supervision of the end user client?
- Personal service:
- Is the contractor required to perform the services personally without the right to send a substitute? If there is a right to appoint a substitute is this subject to end user client approval?
- Mutuality of obligation:
- Is the end user client obliged to provide the contractor work with a mutual obligation on the contractor to accept that work?
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.