What is the reaction to the funding?
The reaction from NCVO is that this is an important first step. However, it will not stop well run charities from closing and others will look very different in a few months’ time.
Related FAQs
The Government’s guidance says walk, cycle or drive to work and avoid public transport if you can. Businesses will need to support workers in adopting alternative travel methods to reduce exposure to the virus. You could consider staggering start and finish times for shifts to reduce commuting during peak hours, or support cycling with secure storage facilities and a drying room.
The amount an insurer charges for providing cover is a critical aspect of the underwriting process. The premium must be sufficient to cover expected claims but must also take into account the possibility that the insurer will have to access its capital reserve –it is risk assessment based and the greater the risk, the higher the premium. Historically, insurers of high-rise buildings would have only had to prepare for a loss caused by damage to just a few flats within a building. That is because the design and construction of that building, with the right materials and fire safety provisions in place, should have limited the spread of fire and allowed the damage to be contained –or at least make this an extremely low risk. Now we know that many buildings have been designed, built and signed off in a regulatory system that an independent Government review has found was not fit for purpose. Premiums will reduce overtime but will be dependent upon the perceived level of risk reducing as the regulatory regime, BSA and BSR become more established.
Ultimately closing a service will be a decision that is taken at the highest level and that decision will depend on risk appetite. Often these types of higher risk are mitigated by way of insurance but that still depends on an insurer being willing to accept that risk. This decision will depend on accepting a known risk and its consequences.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.
With time and resource precious commodities, focus should be given to documenting:
- The key changes to your PFI requirements
- The temporary nature of the measures
- The requirement for best efforts on behalf of the PFI Contractor
- The importance of continued health and safety measures at all times