Can I argue that my contract has been frustrated?

It could be possible depending on your contract. If there is no force majeure clause in a contract, it may be possible that the contract may have been “frustrated” by emergency legislation. In legal terms, a contract can be frustrated where an event occurs after it is entered into which was not contemplated by any party at the outset, is not due to the fault of any party, and which makes the performance of the contract impossible.

If this is the case, the contract could be “discharged”, meaning that the parties’ obligations under the contract are no longer binding.

It is possible that a contract could be frustrated within this particular legal doctrine by a change in the law that makes performance of a contract illegal. However, if it simply becomes more difficult, or more expensive, then the legal tests for frustration might not be satisfied. There are also limits to the application of the rule if the frustrating event was already known about at the time the contracted was entered into.

Again, careful legal advice will be required at an early stage. The rules about force majeure or frustration might help businesses that find themselves unable to perform a contract because of the coronavirus outbreak.

Any new contracts that are concluded should expressly deal with the possibility that performance might become more difficult, more costly, or impossible to perform.

What are the special considerations for DB schemes?
  • Before any agreed reduction in wages, actual changes to earning patterns (loss of overtime, for example) may impact the pensionable salary as defined under the scheme rules, with knock-on effects to a number of benefit calculations, such as death in service benefits.
  • Contractual changes to member salaries may adversely impact accrued benefits as the final salary figure may be reduced to a greater or lesser extent depending on the duration of furlough and the severity of any reductions in wage, and hence reductions may be difficult to agree with staff.
  • Reducing employer contributions will be subject to a number of the same considerations applicable to a DC scheme listed above. There will also be a need to change the rules and interact with the trustees, although it may be possible to override the rules with a direct contractual agreement with members.
  • Reducing employee contributions will also depend on the scheme rules, particularly as to whether there are any discretionary powers to suspend contributions, or pensionable service.
  • The rules will need to be considered for any unexpected consequences of furlough: depending on the wording of the rules, furlough may or may not be considered a leave of absence and may or may not have the effect of terminating pensionable service. This could have far-reaching consequences.
  • In particular, if the workforce’s pensionable service is inadvertently terminated as opposed to suspended in accordance with any relevant rule, this could trigger a statutory employer debt on an employer participating in a multi-employer scheme, if pensionable service continues for employees of other employers. This sort of issue is unlikely to be spotted until after the event, and therefore difficult to untangle. However, an employer should be able to take advantage of the “period of grace” provisions by notifying the trustees of its intention to re-admit employees to pensionable service within the next 12 months.
  • Clearly the impact of the Coronavirus Job Retention Scheme on DB schemes is complex and legal advice should be sought before any changes are considered.
What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

What is the government's "Kickstart Scheme"?

This scheme is specifically aimed at creating jobs for 18-24 year olds who are on Universal Credit and considered most at risk of unemployment because of the economic downturn. The Government has announced that it will pay young people’s wages (equivalent to 100% the National Minimum Wage plus the associated National Insurance contributions and employer minimum automatic enrolment contributions) for up to 6 months, and that this will amount to a grant worth approximately £6,500 per young person.

The jobs that are created must provide a minimum of 25 hours per week and be paid at a minimum of the National Minimum Wage The Chancellor announced that will be no cap on the number of jobs that will be funded under the Kickstart scheme.

Are permitted development rights now in existence for the creation of emergency medical facilities?

Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:

  • Preventing an emergency
  • Reducing, controlling or mitigating the effects of an emergency
  • Taking other action in connection with an emergency

It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.

The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.

Further detail of the permitted development right is available at the link below.

http://www.legislation.gov.uk/uksi/2020/412/made