What is the penalty for failing to comply with the collective consultation obligations?
Failure to comply with the collective inform and consult obligations could impact on the fairness of any dismissals – see next question. In addition, a Tribunal can award a protective award of up to 90 days gross pay for each affected employee. The purpose is intended punish the employer for not complying with the obligations, not to compensate the employee for their individual financial loss.
Related FAQs
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
Some commercial tenants have queried whether the current situation is a force majeure which may allow it to terminate the lease. Clauses which allow a party to terminate a lease for a force majeure event or, to put it another way, an “act of God”, are however extremely rare in modern commercial leases. Even if there is such a provision in your lease, it would need to be drafted to apply to an outbreak of disease.
A licence to occupy premises is not an interest land and operates as a commercial contract between the parties that enter into it. Licences tend to be put in place to cover short periods and consequently they are generally a lot more flexible than commercial leasing arrangements. To that extent occupants under licences should review the contract to establish whether or not there are any provision allowing them to terminate on notice to the Licensor.
Occupants under licences that are granted for longer periods without the option to terminate may try to argue that the contract has frustrated because they are effectively unable to occupy.
No. No action need be taken in relation to the demand but we would advise against presentation of a petition based upon any Statutory Demand issued between 1 March 2020 and the end of the restrictions. As you may be aware, with Winding Up there is no requirement to issue a Statutory Demand notice before proceeding so this is unlikely to create too many issues – click here to see whether you should issue petitions on other grounds.
There is nothing to prevent statutory demands being served at this time. However, there may be limited benefit as it cannot form the basis of a future winding up petition.
As the coronavirus outbreak continues to develop, we have seen many countries begin to implement emergency procedures and legislation in an attempt to control the spread of the disease.
These have included bans on gatherings and public events, closures of shops, bars, restaurants and public spaces, and full lockdowns which restrict all but key workers to their homes except in certain limited circumstances.
This has a direct impact on businesses and their ability to operate. So what happens if a contract becomes impossible to perform because of emergency legislation?
For example:
- If you are a hospitality business, you have agreed to host an event, and gatherings are prohibited
- If you are a manufacturer or service provider, and your staff are required to remain at home, making performance of the contract impossible