What is the new process for assessing status under IR35?
The end user client will be responsible for assessing if the contractor is employed or self-employed for tax purposes. It is required to take reasonable care in carrying out the assessments.
When an assessment is carried out the outcome must be confirmed to the contractor with accompanying reasons in a Status Determination Statement (SDS). This SDS must be provided to the contractor before making payment to them. It must also be provided to the agency if there is one in the chain (more on this later).
The end user client must have a dispute resolution procedure to enable to the contractor or agency to appeal the assessment outcome.
Related FAQs
There are two stages:
- Stage 1 – The provision of written information to the representatives.
- Stage 2 – Consultation on the proposed redundancies “with a view to reaching agreement” about certain matters
Stage 1: Provision of information
The first stage in the collective consultation process is to provide the representatives with written information including details of the proposed redundancies (often called a section 188 letter). This information must be given to the appropriate representatives and the time limit before dismissals can take effect does not start to run until they have received it. It is this information which ‘starts the clock’.
It is possible that there will be changes to the proposals during the consultation process: indeed that is part of the reason for the process. The employer’s obligation is not just to provide the appropriate representatives with the relevant information at the start of the process. It is under a continuing obligation to provide them with information in writing about any developments during the consultation process (although later changes do not ‘restart the clock’ before dismissals can take effect).
Stage 2: Consultation on the proposed redundancies “with a view to reaching agreement” about certain matters
The consultation process must include consultation “with a view to reaching agreement with the appropriate representatives” on ways of:
- Avoiding the dismissals
- Reducing the number of employees to be dismissed
- Mitigating the consequences of the dismissals
Yes but the sponsor must report this on the Sponsor Management System within 10 working days and must follow normal employment law principles.
If this results in the sponsored worker’s falling below the minimum required salary the usual position is that they cannot continued to be sponsored. However the government has implemented a concession for sponsors who have ceased trading or temporarily reduced trading which allows the salary to be reduced to 80% of the figure stated on the Certificate of Sponsorship or £2,500 per month, whichever is lower.
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.
New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.
For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.
Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.
For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.
Ultimately closing a service will be a decision that is taken at the highest level and that decision will depend on risk appetite. Often these types of higher risk are mitigated by way of insurance but that still depends on an insurer being willing to accept that risk. This decision will depend on accepting a known risk and its consequences.