What is the new Permitted Development Right for the construction of new dwellinghouses?
A new Permitted Development Right has been introduced by The Town and Country Planning (Permitted Development and Miscellaneous Amendments) (England) (Coronovirus) Regulations 2020 providing for the construction of new dwellinghouses on detached blocks of flats.
The new Right comes into force on 1 August 2020 and from this date development consisting of works for the construction of up to two additional storeys of new dwellinghouses immediately above the existing topmost residential storey which is a purpose-built, detached block of flats is permitted development. The Right additionally covers specified associated works, the construction of fire escapes and ancillary structures, bin stores for example.
The Right is subject to detailed criteria being met and to a prior approval process to the Local Planning Authority who can consider the acceptability of the proposed development in a range of respects. A link to the Regulations is here.
The Regulations additionally include a number of further amendments including additional rights for the holding of markets and for additional temporary uses of land for a time limited period. They additionally include amendments to existing permitted development rights for the change of use of buildings to dwellinghouses through a requirement that there be adequate natural light in all habitable rooms.
Related FAQs
- Working with PFI providers to get contingency plans up to date
- If a PFI provider is struggling to achieve service delivery requirements due to Covid-19, then local arrangements should be put in place to:
- maintain unitary charge payments
- revise contract requirements/standards
moderating payment and performance regimes where appropriate.
- In any event, you may wish to review and adjust your requirements to reflect the current situation. It is possible that some requirements can be relaxed, whereas others need to be tightened. For example, there may be an increased need for cleaning and maintenance in certain areas of your PFI premises or the layout of the premises and/or room uses may have temporarily changed. With staff illness and shortage likely to be an issue, you may also wish to consider if the resource can be moved from one area to another to help maintain essential services.
- When putting local bespoke arrangements into place it is vital that:
- Contract requirements or performance standards are not relaxed to the point where health and safety are put at risk.
- It is made clear that the arrangements are temporary and that matters will return to normal as soon as the Covid-19 emergency is over. Indeed the guidance note makes clear that if assets temporarily close they should be kept in such condition that they can be immediately up and running when this emergency is over. In such instances, likely a basic level of maintenance and security will therefore be required as a minimum.
This is likely to be a common situation and employers and employees are going to have to take a pragmatic approach. You could enter into a temporary flexible working arrangement perhaps agreeing to vary working hours/days or reducing targets or agree to use some annual leave.
Employees could ask to take a period of unpaid leave, asserting their right to time off to care for a dependant but the lack of pay is likely to be unappealing.
Alternatively employees who are unable to work because they have caring responsibilities as a result of COVID-19, which includes childcare responsibilities, can be furloughed.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
Where one or more of the parties is represented, responsibility for making the arrangements for the remote hearing will fall on either the applicant or the first represented party. If no party is legally represented, the court office will contact the parties to explain that the hearing will be held by telephone conference and will send them instructions on how this is to be achieved.
All remote hearings must be recorded. The responsibility for arranging the recording will be addressed on a case by case basis.
Safeguarding issues are relatively uncommon, however, if they do occur, the normal safeguarding procedure of the organisation should be followed.