What is the new Permitted Development Right for restaurants, cafes and drinking establishments?
A new Permitted Development Right has been introduced providing restaurants and cafes, drinking establishments with expanded food provision to temporarily provide takeaway food. The new right came into force on 24 March 2020 and expires on 23 March 2021. The right is subject to three conditions:
- The developer must notify the local planning authority if the building and any land within its curtilage is being used, or will be used, for the provision of takeaway food at any time during the relevant period
- Change of use to the provision of takeaway food under the Right, does not affect the use class which the building and any land within its curtilage had before the change of use
- If the developer changes use to the provision of takeaway food under the Right, the use of the building and any land within its curtilage reverts to its previous lawful use when the Right expires or, if earlier, when the developer ceases to provide takeaway food.
Alcohol will still be subject to the same licensing requirements. At this stage, it is not clear how the Right will interact with any current planning conditions placed on an establishment. Enforcement however remains discretionary. A link to Statutory Instrument 2020 No.330 is below.
Related FAQs
Potentially, yes. If someone refuses to follow the health and safety measures that have been put in place to protect them, colleagues and possibly their customers, including (where appropriate) the use of PPE then this is a disciplinary issue and should be dealt with as such. Repeated failure to comply with the requirement to follow these measures, or a one off significant failure, may be sufficient to justify dismissal, depending on the circumstances.
If you are eligible you will get a taxable grant of 80% of the average profits from the following tax years (where applicable):
2016-2017
2017-2018
2018-2019
HMRC will add the total profit in each of the three tax years (if applicable). This will then determine the monthly payment, subject to the cap of £2500.
As above, employees must not leave their home unless they have a ‘reasonable excuse’.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
- Integration:
- Is the individual held out as being employed by the business by having a company email address, uniform, how would they introduce themselves to customers?
- Exclusivity:
- Is the contractor restricted from working for other organisations without the consent of the end user client?
- Length of engagement:
- Is the contractor engaged to work on a specific project for a defined period? Or are they engaged for an indefinite period with no reference to a specific task or project?
- Pay:
- Are there regular fixed payments or is payment on completion of specific task or commission based? Is the contractor entitled to benefits or bonuses?
- Facilities:
- Does the contractor provide their own equipment and materials to provide the services?
- Financial risk:
- Is the contractor personally responsible for any loss arising from their work in performing the services? Will they have to rectify unsatisfactory work at their own time and expense? Will they have the opportunity to profit from the success of a project?