What is the “Job Retention Bonus”?
As a result of the CJRS being extended, the Job Retention Bonus will no longer be paid in February 2021.
Related FAQs
Yes. The system for Probate Applications has moved on-line and continues to be available as well as by post. However, if you need to complete an Inheritance Tax Return IHT400 you are likely to experience problems collating information due to delays in many organisations being able to provide you with current values while their offices are closed and staff working remotely. Property valuations will be particularly problematic where surveyors or valuers are unable to attend properties to undertake non-urgent work. If you cannot wait, you must use your best endeavours to be as accurate as possible as regards the information you provide in the IHT400 and follow up by providing HMRC with actual values as soon as you can do so. HM Courts and Tribunal Service is however warning that delays can be expected at this time.
In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:
- Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
- Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
- Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
- Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
- Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
- Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
- Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
- Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
- Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!
In general. there is often a stick or twist decision. If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful. Conversely, withholding payments from the contractor may make insolvency a self-fulfilling prophecy. The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.
The Government has produced workplace guidance for employers, setting out 2 key messages for employers:
- Continue to make workplaces as safe as possible; and
- Encourage workers to heed any notifications to self-isolate and to support them while they are require to isolate
Government guidance can be accessed here: How it works (an overview) and Workplace guidance for employers.
Parties are encouraged to review upcoming matters to assess the viability for there to be any agreement which can be reached in relation to the issues in dispute or to consider whether the case needs to proceed to a remote hearing. If directions or issues can be agreed between the parties, reducing the need for remote hearings, then that is the preferred option.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.