What is the Flexible Furlough Scheme?
The Flexible Furlough Scheme, ‘FFS’ an unfortunate acronym, allows employees to work for some of the week and be furloughed for the rest.
Related FAQs
The end user client will be responsible for assessing if the contractor is employed or self-employed for tax purposes. It is required to take reasonable care in carrying out the assessments.
When an assessment is carried out the outcome must be confirmed to the contractor with accompanying reasons in a Status Determination Statement (SDS). This SDS must be provided to the contractor before making payment to them. It must also be provided to the agency if there is one in the chain (more on this later).
The end user client must have a dispute resolution procedure to enable to the contractor or agency to appeal the assessment outcome.
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.
- Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
- Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
- Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
- The ability to get people on site to undertake material operations
In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.
If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.
It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved. To be in the best possible position, it is worth considering the following at the outset of any project:
- Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
- Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
- Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
- Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
- Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
- Project bank accounts and escrow accounts can also provide some further assurances for the parties involved
Residents will be obliged to:
- Not act in a way that creates a significant risk of a building safety risk materialising
- Not interfere with building safety equipment in the common parts
- Comply with an Accountable Person’s request for information in relation to the assessment and management of building safety risks.
The Accountable Person then has powers in relation to these duties, including:
- Issuing a contravention notice, requiring a resident to pay for replacement or repair of safety equipment which they have interfered with
- Applying for court orders in certain situations
- Requesting access at a reasonable time (in writing with at least 48 hours’ notice) to a resident’s property for the purposes of assessing or managing building safety risks, or checking compliance with the resident’s duties as above.
Secondary legislation is still awaited to bring these provisions into force, so the timing is unknown, but it will likely be within the next 12 months in line with the anticipated timetable for the remainder of the Act.