Skip to content

What is the difference between individual and collective consultation?

Where it is envisaged that 20 or more employees will be dismissed at a relevant establishment within a 90 day period or less, then collective consultation is required (in addition to individual consultation) and the company must inform BEIS (using form HR1).

If there are less than 20 dismissals then you are only required to carry out individual consultation.

Related FAQs

What should businesses do now?

Many will have worked collaboratively with their suppliers and customers to deal with the immediate public health crisis. This will have meant offering flexibility as to contractual arrangements, whether in delivery dates, volumes of goods or services supplied, or even in the specification of what has been delivered.

If this is the case, it is important that businesses now do their legal housekeeping and make sure they have a proper record of what has been agreed. Unfortunately, our experience shows that many legal disputes arise out of amendments to contracts, typically where the parties to the contract each have a different view about what exactly they agreed to change.

We would therefore advise businesses to review any amendments that they might have agreed either verbally, by email, or otherwise, and consider whether they need to be captured in a more formal way which will make clear exactly what has been agreed to be varied, and (where appropriate) how long that variation will remain in force.

It’s also important to remember that some contracts contain provisions that set out specific requirements about how amendments are to be made. For example, they might require that amendments are made in writing (rather than verbally). These “No Oral Modification” clauses are commonly found in commercial contracts, and the courts have recently shown that they are willing to enforce them.

Failing to deal with amendments in accordance with contractual requirements could therefore have a serious impact on businesses as they recover from the disruption caused by the lockdown. If they end up in dispute with a customer or supplier, a business could find that the contract has not actually been amended in the way that they think – potentially leading to legal costs and liabilities at the worst possible time.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

What is the most important thing employers should do from a health and safety perspective?

Conduct risk assessments! Your RA must cover every foreseeable risk arising from a return to the workplace, including the impact of reduced staff levels and any operational/administrative changes necessary to ensure social distancing.

Appropriate steps should be taken to manage and mitigate identified risks. Where this is not possible, businesses need to decide whether certain activities are necessary for the business to operate or if they can be temporarily put on hold.
Keep a close eye on the comprehensive Government guidance: https://www.gov.uk/guidance/working-safely-during-coronavirus-covid-19

In particular focus on social distancing and workplace health measures. This guidance will evolve over time and you will need to be sure that your organisation is sticking to it AND reviewing and updating its risk assessment.

What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

What is the new Permitted Development Right for the construction of new dwellinghouses?

A new Permitted Development Right has been introduced by The Town and Country Planning (Permitted Development and Miscellaneous Amendments) (England) (Coronovirus) Regulations 2020 providing for the construction of new dwellinghouses on detached blocks of flats.

The new Right comes into force on 1 August 2020 and from this date development consisting of works for the construction of up to two additional storeys of new dwellinghouses immediately above the existing topmost residential storey which is a purpose-built, detached block of flats is permitted development.  The Right additionally covers specified associated works, the construction of fire escapes and ancillary structures, bin stores for example.

The Right is subject to detailed criteria being met and to a prior approval process to the Local Planning Authority who can consider the acceptability of the proposed development in a range of respects.  A link to the Regulations is here.

The Regulations additionally include a number of further amendments including additional rights for the holding of markets and for additional temporary uses of land for a time limited period.  They additionally include amendments to existing permitted development rights for the change of use of buildings to dwellinghouses through a requirement that there be adequate natural light in all habitable rooms.