Skip to content

What is the current guidance relating to Private Finance Initiatives and PF2 Projects in light of coronavirus?

On 2 April 2020, the Government issued guidance relating to Private Finance Initiatives and PF2 Projects. The guidance, which is to be enforced with immediate effect (currently due to stay in place until 30 June 2020), is one of several guidance notes issued to date.

A link to the guidance is set out below:

https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/877804/2020_04_01_PFI_and_COVID19_final.docx.pdf

Key messages to contracting authorities

  • PFI contractors should very much consider themselves as being part of the public sector response to the current pandemic
  • Covid-19 is not regarded as, and is not to be classified as a force majeure event
  • PFI contractors must ensure that contingency plans are up to date and have been reviewed and discussed with contracting authorities to enable the continuity of full services to respond to the pandemic and maintain vital public services
  • Contracting authorities should work closely with PFI contractors to use all available options to maintain public services during the emergency period
  • Local arrangements should be made where PFI contractors can’t deliver the agreed requirements and performance standards
  • “Best efforts” should be made by all parties for the continuation of service provision

Related FAQs

Is there any guidance available for COP proceedings during Covid-19?

The Vice President of the COP, Mr Justice Hayden, has issued guidance to assist parties during this challenging time.

The latest guidance with all relevant updates on developments is available on the judiciary website here.

What will be the impact of the proposals on suppliers?

The change in the law has the potential to place much greater financial risks on suppliers, making it more difficult to exit a contract with a customer of doubtful solvency.  This will place increased emphasis on appropriate financial due diligence and credit checking before entering into supply contracts.

In addition to the obvious issues around financial risk, suppliers will also need to think carefully about how their contracts are drafted.  For example, any form of right that is drafted so as to be triggered on customer insolvency will clearly be problematic.  These could include:

  • Retention of Title provisions, which are commonly drafted so that the right to enter premises and retake possession of the goods is triggered on insolvency;
  • Provisions for brand protection, which seek to control how goods are dealt with on termination of the contract.

This is potentially a very significant development for many businesses.  We would strongly recommend specialist advice be obtained so that:

  • businesses understand the potential increased risks faced; and
  • where possible, contracts are updated so that appropriate protections are maintained.
How does this protect businesses entering into an insolvency process?

The Act is intended to facilitate the rescue of businesses that are in financial difficulty by preventing suppliers from invoking certain termination clauses under a supply contract, and therefore maintaining supply of goods and services to the business whilst plans to save the business can be considered.

Supply contracts often contain a clause enabling them to terminate the contract, or take other steps such as requiring payment in advance,  in the event that the customer enters an insolvency procedure.

This new Act removes any such contractual right by dis-applying any clause that allows the supplier to terminate the contract, or take any other step, due to the customer entering an insolvency process.

Suppliers are also prevented from demanding payment for pre-insolvency debts owed by the customer as a condition of continued supply.

Additionally, where the supplier had a contractual right to terminate the contract due to an event occurring before the customer went into the insolvency process (whether or not linked to payment issues), the supplier loses this right for the duration of the insolvency process.

Is there a matched funding scheme for the National Emergencies Trust?

The government has also confirmed it will match donations to the National Emergencies Trust as part of the BBC’s Big Night In fundraiser on 23 April – pledging a minimum of £20 million.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here