What is the claim period for Flexible Furlough?
Employers had until 31 July 2020 to make any claims for claim periods up to 30 June 2020. That was the end of the old scheme.
From 1 July 2020, claim periods must start and end within the same calendar month and must be for at least 7 days unless you are claiming for the first few days or the last few days in a month.
You can only claim for a period of fewer than 7 days if the period you are claiming for includes either the first or last day of the calendar month, and you have already claimed for the period ending immediately before it.
For example, if an employee is furloughed for 7 days spanning a month. You can claim the last 3 in one month, and 4 from the next.
The crucial point is that you cannot make claims that cross calendar months.
The first time that you could make a claim for days in July 2020 was 1 July 2020. You could not claim for periods in July 2020 before this point.
Related FAQs
A claim for indirect discrimination is the most likely risk here. The first point to make is that the decision to review duties is being made based on the growing amount of medical evidence that the BAME community is being disproportionately adversely affected by the COVID 19 pandemic compared to other ethnic groups. The key is to ensure that blanket policy decisions are not taken, nor should assumptions be made about the risk to each individual concerned. Decisions should only be made on an individual basis with an open dialogue with the individual concerned. You as their employer, need to ensure that the individual feels listened to and heard; that this is not just a tick box exercise.
Consider having a working group which has an overview of the policy decisions being made. That working group should contain representatives from across the staff groups including staff side, but importantly, representatives from different ethnic backgrounds to ensure the important voices are heard. Accountability should be built into that group. This group should also be a safe environment for staff to raise concerns about their health and safety and safe systems at work.
Due to the new guidance on social distancing and remote working, the Planning Inspectorate initially stated that site visits, hearings and inquiries would be cancelled. However, there is very much a push from the Secretary of State to keep the planning system moving notwithstanding the requirements to adapt to new ways of working. The Government now expects all hearings to be conducted virtually and where a virtual hearing is not possible, the expectation is that alternative arrangements will be put “speedily” in place and in accordance with social distancing requirements.
The Planning Inspectorate have been exploring ways of conducting hearings and inquiries remotely using technological means and conducted their first “digital” hearing on 11 May .
The Business and Planning Act 2020, which entered the statute books on 22 July 2020, includes provisions which allow more flexibility in relation to how appeals are determined including an ability for the Secretary of State to decide to adopt a procedure which is a combination of written representations, a hearing and/or an inquiry.
Site visits have re-commenced where it is safe to do so. The Inspectorate is looking at whether a site visit is necessary and has conducted a trial of “virtual site visits” where sites are assessed by means of photographs or video evidence.
The Planning Inspectorate have subsequently been scaling up conducting digital hearings, which also includes holding virtual local plan examination hearings.
All three of the PPNs are effective immediately and apply to the following Contracting Authorities:
- Central Government Departments
- Executive agencies
- Non-departmental public bodies
- Local authorities
- NHS bodies
- The wider public sector
In regards to PPN03/20, those in scope organisations that do not currently use procurement cards are advised to immediately put in place arrangements using the relevant Crown Commercial Service Agreement (Lot 2 of RM3828 Payment Solutions).
Despite remote hearings being the default position at present, formal permission will still be required by the court and a template order was circulated with the guidance. This template sets out the relevant directions and recitals to include in your order. An application to the COP for a remote hearing will not be required.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.