Skip to content

What is the claim period for Flexible Furlough?

Employers had until 31 July 2020 to make any claims for claim periods up to 30 June 2020. That was the end of the old scheme.

From 1 July 2020, claim periods must start and end within the same calendar month and must be for at least 7 days unless you are claiming for the first few days or the last few days in a month.

You can only claim for a period of fewer than 7 days if the period you are claiming for includes either the first or last day of the calendar month, and you have already claimed for the period ending immediately before it.

For example, if an employee is furloughed for 7 days spanning a month. You can claim the last 3 in one month, and 4 from the next.

The crucial point is that you cannot make claims that cross calendar months.

The first time that you could make a claim for days in July 2020 was 1 July 2020. You could not claim for periods in July 2020 before this point.

Related FAQs

My business involves providing services to consumers. What are my legal obligations in relation to deposits paid by consumers for services that I have been unable to perform due to government restrictions?

Many businesses that supply directly to consumers have been concerned to understand their legal position in relation to services that have been cancelled, or that they have been unable to perform, because of the Covid-19 pandemic, and in particular how to deal with deposits paid by consumers for such services. With some degree of restriction on the hospitality and tourism sectors likely to remain in place for some time, such questions will remain important for the foreseeable future.

What do we do if we cannot meet the Court directions order / timetable?

An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.

Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.

In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.

The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.

What should I do if the contractor is in suspected financial difficulty?

In the event that the contractor is displaying one or more of the above signs, then it is worth considering the following actions to protect the employer’s position as far as possible:

  • Closely monitor the financial and on-site performance of the contractor in order to assess the likelihood and timing of potential insolvency
  • Ensure all bonds, guarantees and collateral warranties have been obtained under the building contract, and if not take steps to obtain them immediately
  • Consider the terms of any guarantees to ensure that the guarantor’s obligations are not inadvertently discharged
  • Bonds may require adjudication to have been commenced (or even completed) prior to insolvency so as not to be stayed pursuant to insolvency laws
  • Carry out an audit of the on-site plant, equipment and materials, and evidence this (for example with photographs and written records)
  • Ensure that copies of all relevant documentation have been obtained, for example drawings, specifications and anything required to comply with CDM requirements. If not, take steps to obtain these
  • Review the payment position under the building contract, including whether any over payments have been made to the contractor which should be reclaimed, what retention is held or has been released, whether any payment notices may be necessary, and whether there are rights of set-off which should be exercised
  • Check whether the involvement of any third party is required, for example funders, landlords, tenants or purchasers who may have rights in relation to the building contract and how it is administered
  • Review the terms of the building contract relating to contractor insolvency – hopefully the parties will be fully aware of the building contract terms and have been administering it correctly to date, but if it has been hiding in a draw then now would be a good time to dust it off and ensure familiarity with the relevant provisions!

In general. there is often a stick or twist decision.  If the employer chooses to financially support the contractor (for example by agreeing different payment arrangements), this may help to keep the contractor solvent and more likely to complete the project, but it also exposes the employer to greater risk if the approach is not successful.  Conversely, withholding payments  from the contractor may make insolvency a self-fulfilling prophecy.  The precise advantages and disadvantages of the approach will be dependent on the specific circumstances of each case.

I work in construction. Can I still travel to work?

The CLC has also prepared a template letter that firms may adopt and issue to their workforce regarding travel to work. This can be accessed at download document.

The CLC’s current advice to those carrying out works on site is to carry out your own risk assessment on each site and determine whether or not it is safe to continue to work in accordance with the Public Health England instructions and the CLC Site Operating Procedures.  If it is not possible to work in accordance with the above they should not work.

Do I still need to pay instalments of Community Infrastructure Levy (CIL) while the development site is closed?

Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.

New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.

For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.

Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.

For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.