Skip to content

What is the claim period for Flexible Furlough?

Employers had until 31 July 2020 to make any claims for claim periods up to 30 June 2020. That was the end of the old scheme.

From 1 July 2020, claim periods must start and end within the same calendar month and must be for at least 7 days unless you are claiming for the first few days or the last few days in a month.

You can only claim for a period of fewer than 7 days if the period you are claiming for includes either the first or last day of the calendar month, and you have already claimed for the period ending immediately before it.

For example, if an employee is furloughed for 7 days spanning a month. You can claim the last 3 in one month, and 4 from the next.

The crucial point is that you cannot make claims that cross calendar months.

The first time that you could make a claim for days in July 2020 was 1 July 2020. You could not claim for periods in July 2020 before this point.

Related FAQs

Can I still take legal action to recover money that is owed to the business?

You will need to check the terms of the contract you have with the debtor to make sure you are still entitled to be paid (including checking any force majeure clause).

It is also important to remember that the current exceptional circumstances might also affect your contractual rights in other ways too – please see our commercial & contracts site for more information.

Depending on the type of debt you are owed, there might be some additional restrictions in place that you will need to consider. For example there are certain restrictions on landlords being able to forfeit leases, evict tenants or send High Court Enforcement Officers to collect outstanding rent.

Assuming there are no sector-specific restrictions in place then you should be able to start county or high court proceedings to recover the debt.

As an alternative to starting court proceedings, if the debt is undisputed a creditor can usually opt to issue winding up proceedings against a debtor instead. However, the recently introduced Corporate Insolvency and Governance Act introduces a temporary suspension on the ability of creditors to present winding up petitions to recover money unless the reason why the debtor cannot pay is not related to covid-19. For more information click here.

Often taking firm action is the right thing to do, particularly given that it is a sad reality that it is the creditor who shouts the loudest that will often get paid first. However, one important consideration is the commercial reality that many businesses (and indeed individuals) now find themselves in.

Whether taking legal action is likely to result in payment is always a question any creditor should ask themselves. Some creditors might also want to try to support their customers during these difficult times and/or have concerns about their long term reputation if they pursue the debt too aggressively. However, even if that is the case it is still possible to engage constructively and positively with those who owe you money to try to reach the best possible outcome. This could include:

  • Having clear and consistent credit control processes in place
  • Obtaining statements of means to help understand what a debtor can afford to pay
  • Agreeing realistic payment plans
  • Negotiating formal payment holidays
  • Putting in place voluntary security to secure the debt
  • Identifying those debtors who can’t pay as opposed to won’t pay and targeting resources accordingly
  • Looking at what other options might be available, including recovering under parent company guarantees
Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

What are the changes to the law?

On 25th June 2020, the Corporate Insolvency and Governance Act, among other things, introduced new restrictions on suppliers of goods and services to terminate the contract in the event that the customer enters an insolvency process.  This has very important consequences for many businesses as it could expose them to greater financial risks.

Do I still need to pay instalments of Community Infrastructure Levy (CIL) while the development site is closed?

Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.

New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.

For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.

Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.

For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.

What are my potential liabilities if a customer, supplier or other visitor contracts Covid-19 on my premises?

As an occupier of premises, you owe a duty of care to your visitors to take reasonable care to see that the visitor will be reasonably safe in using your premises.

It is therefore essential that you are taking reasonable steps and strictly adhering to up-to-date Government advice in all aspects of your business to avoid any potential liability.

Failure to follow Government advice could leave you vulnerable to claims for compensation for pain and suffering should a visitor on your premises contract Covid-19.

However, each case will be fact-specific and it would be very difficult for a visitor to establish that they contracted Covid-19 specifically from those premises (as opposed to being exposed to the virus anywhere else).

If someone suggests that they are going to make a claim make sure that you report matters to your insurer or insurance broker immediately.