Skip to content

What is happening about court and arbitration hearings?

The courts are seeking to adapt to our new circumstances and have urgently been looking to introduce new ways of working. The courts have been testing out different ways of holding court hearings. The advice is changing almost daily and some courts have been developing local practices. Going forward the court, the parties and their representatives will need to be more proactive about all forthcoming hearings.

Everyone involved in the case is to consider as far ahead as possible how future hearings should best be undertaken and work collaboratively. It will normally be possible for all short, interlocutory, or non-witness, applications to be heard remotely. Some witness cases will also be suitable for remote hearings. The parties just need to ensure that everyone involved can use the technology suggested.

The courts have been looking at and held remote hearings using, non-exhaustively, BT conference call, Skype for Business, court video link, BT MeetMe, Zoom and ordinary telephone call. Bundles for the hearing will be prepared and circulated electronically.

If the hearing cannot be held remotely because the parties do not have the requisite technology or the length of the hearing combined with the number of parties or overseas parties, representatives and/or witnesses make it undesirable to go ahead with a hearing in court at the current time, then it may be that the case will need to be adjourned. We are hearing of trials being adjourned and that they will not be re-listed before at least September.

HMCTS has advised that several priority courts will remain open during the coronavirus pandemic to make sure the justice system continues to operate effectively. It publishes a daily operational update from the courts and they aim to update it by 9am. The link is https://www.gov.uk/guidance/hmcts-daily-operational-summary-on-courts-and-tribunals-during-coronavirus-covid-19-outbreak.

Also, the courts have circulated a civil listing priority list with Priority 1 listing work which must be done and which includes injunctions, any applications in cases listed for trial in the next three months, any applications where there is a substantial hearing listed in the next month and all Multi Track hearings where parties agree that it is urgent.

In the Priority 2 list, which consists of hearings which could be done, are enforcement of trading contracts, trial involving the survival of a business or the insolvency of an individual, small and fast track trials where the parties say they are urgent, and appeal in these kinds of cases.

Similarly, in arbitration proceedings, the parties and arbitrators are being encouraged to utilise technology to make sure that hearings take place. We have heard of Zoom being used very successfully for multi-party proceedings.

Related FAQs

What impact does the Regulations have in respect of matters which arise from Fire Safety Audits - e.g. if balconies with wooden/decking elements are now considered higher risk and whether that would fall to developer to remedy the materials used to construct balconies?
The duty would fall on the owner of the building to control the hazards presented by balconies made from combustible materials. There may be scope (via warranties/indemnities or other terms) arising from the contract between the developer and owner for the owner to seek to recover the cost of remedial works.
Is there a matched funding scheme for the National Emergencies Trust?

The government has also confirmed it will match donations to the National Emergencies Trust as part of the BBC’s Big Night In fundraiser on 23 April – pledging a minimum of £20 million.

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

Are the Courts still open and operating?

Yes, but the Courts have been temporarily restructured into three categories:

  1. Open courts (open for business including vital in person hearings)
  2. Staffed courts (for video and telephone hearings)
  3. Suspended courts (no hearings of any kind)

These changes have been effective from Monday 30 March 2020.

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here