What is Coronavirus Business Interruption Loan Scheme (CBILS)?
The Coronavirus Business Interruption Loan Scheme (“CBILS“) is open for applications to provide small businesses with a loan of up to £5m to assist with the Covid-19 outbreak. The Scheme is aimed at businesses who are experiencing lost or deferred revenues, and who otherwise would be denied support from lenders, to be supported by a Government backed guarantee. The Scheme will initially run for six months with the possibility to be extended where required, so businesses should only approach a lender under the Scheme as and when they require assistance.
Related FAQs
If a tenant continues to refuse to take heed of the government’s social-distancing guidelines, for example by inviting large groups of people who do not reside there to their property, it can constitute a nuisance. One housing association successfully applied for an injunction. The injunction ordered by the Court stipulated that no persons, other than the children of the tenant, are to attend the property until the current social-distancing restrictions are lifted by the government.
A representative of the housing association highlighted the need for the current guidelines to be followed and the need for housing providers to ensure that all residents living in their communities are kept safe during this time of ‘unprecedented risk’.
This case demonstrates that flouting of the current restrictions is likely to be considered anti-social in the eyes of the courts – a point which all housing providers should bear in mind during this period. Further, it highlights the availability of an alternative remedy to the issuing of possession proceedings (in light of the government’s moratorium on evictions) to deal with anti-social behaviour during the next three months, Covid-19 related or not.
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
The Government’s Corporate Insolvency and Governance Act introduces amendments to the current rules for companies on holding meetings, to address the difficulties companies are facing due to the Covid-19 pandemic.
The new provisions apply to meetings held between 26 March 2020 and 30 September 2020 (referred to as the “Relevant Period”). Subsequent regulations by the Government can be used to shorten this period or extend by up to 3 months but not past 5 April 2021.
The provisions will have retrospective effect, so meetings that were held after 26 March 2020 that may not have met the usual legal requirements due to lockdown, will be validated under these new provisions. These provisions under the Act make amends to relevant legislation and override a company’s articles of association.
For general meetings and certain other meetings of companies, the Act states that:
- The meeting need not be held in any particular place;
- The meeting may be held, and any votes may be cast, by electronic means or other means;
- The meeting may be held without anyone being in the same place
- Persons attending the meeting no longer have the following rights: the right to attend in person, the right to participate in the meeting other than by voting, or the right to vote by particular means.
The aim of these changes is to facilitate virtual meetings, and remove the need for a physical venue.
Where a company was required to hold its AGM between 26 March and 30 September 2020, it can be held at any time before 30 September 2020. The Secretary of State has the power to make regulations to further extend the deadline.
Some of these can be implemented by you, some need agreement or consultation and some depend on the wording of contracts. We’ll explain more in relation to each option.