How has the law changed?
In part in response to the Covid-19 pandemic, legislation was passed by the government earlier this year which sought to assist companies to trade through the current economic climate. Included within the measures is a degree of protection from compulsory winding up.
The Corporate Insolvency and Governance Act 2020 (The Act), was laid before parliament on 20 May, and became law on 26 June. It is important creditors are aware of what changes have been implemented and the potential and impact which it may have upon debt recovery action you may be considering or have already commenced.
The main part of the Act affecting creditors is the temporary restriction on presentation of winding up petitions and the factors that the Court has to take into account when deciding whether to wind up a company.
On Thursday 24 September 2020 the government passed a further statutory instrument which extended the operation of these restrictions. As a result, the measures which were due to expire on Wednesday 30 September 2020 have now been extended until 31 December 2020.
A key point to note is that the Act has retrospective effect so any pending petitions presented after 27 April will be affected, along with any winding up orders made after that date.
The Act has introduced the following restrictions:
- A petition cannot be presented by a creditor during the period of 27 April 2020 and 31 December 2020 unless the creditor has reasonable grounds to believe that (a) coronavirus has not had a financial effect on the debtor, or (b) the debtor would have been unable to pay its debts even if coronavirus had not had a financial effect on the debtor;
- A petition cannot be presented after 27 April 2020 if it is based on a unsatisfied statutory demand served between 1 March 2020 until 31 December 2020;
- When deciding whether to make a winding up order the Court will need to be satisfied that the grounds giving rise to the petition would have arisen even if Covid-19 did not have a financial effect on the debtor;
- All winding up orders made between the 27 April and 31 December will automatically be void (that is, of no legal effect) unless the Court would have made the winding up order if the new law was in force at the time the order was made.
Related FAQs
Specialist healthcare lawyers from Ward Hadaway ran a free webinar looking at the practical and legal considerations if required to treat healthcare workers from a BAME background or other vulnerable groups differently in the fight against the Covid-19 pandemic.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
Some commercial tenants have queried whether the current situation is a force majeure which may allow it to terminate the lease. Clauses which allow a party to terminate a lease for a force majeure event or, to put it another way, an “act of God”, are however extremely rare in modern commercial leases. Even if there is such a provision in your lease, it would need to be drafted to apply to an outbreak of disease.
The Chief Coroner adopts the approach taken by the Lord Chief Justice in that no physical hearing should take place unless it is urgent and essential business, and it is safe for all involved. If a hearing is to take place, social distancing must be maintained. All hearings that can take place remotely should do so, if it is not possible for social distancing requirements to be met. The expectation is that some hearings will go ahead, most notably Rule 23 hearings. Coroners are reminded that they must however conduct any remote hearings from a court. Decisions as to the most appropriate approach will be left to the senior coroner in that jurisdiction.
As we have already seen, some inquests will be adjourned, most notably those with multiple witnesses and/or a jury.
The guidance stresses the need, when dealing with medical professionals, for coroners to recognise their primary clinical commitments, particularly in these high-pressured times. This could mean avoiding or deferring requests for lengthy reports/ statements and accommodating clinical commitments if clinicians are called as witnesses.
The guidance encourages proactive reviews of outstanding responses to Prevention of Future Death reports and extending timescales for Trusts to respond.
As a result of the CJRS being extended, the Job Retention Bonus will no longer be paid in February 2021.