How has the law changed?
In part in response to the Covid-19 pandemic, legislation was passed by the government earlier this year which sought to assist companies to trade through the current economic climate. Included within the measures is a degree of protection from compulsory winding up.
The Corporate Insolvency and Governance Act 2020 (The Act), was laid before parliament on 20 May, and became law on 26 June. It is important creditors are aware of what changes have been implemented and the potential and impact which it may have upon debt recovery action you may be considering or have already commenced.
The main part of the Act affecting creditors is the temporary restriction on presentation of winding up petitions and the factors that the Court has to take into account when deciding whether to wind up a company.
On Thursday 24 September 2020 the government passed a further statutory instrument which extended the operation of these restrictions. As a result, the measures which were due to expire on Wednesday 30 September 2020 have now been extended until 31 December 2020.
A key point to note is that the Act has retrospective effect so any pending petitions presented after 27 April will be affected, along with any winding up orders made after that date.
The Act has introduced the following restrictions:
- A petition cannot be presented by a creditor during the period of 27 April 2020 and 31 December 2020 unless the creditor has reasonable grounds to believe that (a) coronavirus has not had a financial effect on the debtor, or (b) the debtor would have been unable to pay its debts even if coronavirus had not had a financial effect on the debtor;
- A petition cannot be presented after 27 April 2020 if it is based on a unsatisfied statutory demand served between 1 March 2020 until 31 December 2020;
- When deciding whether to make a winding up order the Court will need to be satisfied that the grounds giving rise to the petition would have arisen even if Covid-19 did not have a financial effect on the debtor;
- All winding up orders made between the 27 April and 31 December will automatically be void (that is, of no legal effect) unless the Court would have made the winding up order if the new law was in force at the time the order was made.
Related FAQs
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
The basics of health and safety law requires that employers take “all reasonably practicable steps” to ensure workers’ safety and that a suitable and sufficient assessment of risk is undertaken. It is the individual assessment of Covid-19 risk in each workplace that will be central. Employers will be required to conduct a robust risk assessment and then, following the hierarchy of controls, put robust processes and safeguards in place to address those risks.
UK government guidance and HSE advice is continually evolving, which in practice means that any risk assessment will need to be reviewed very regularly as that guidance develops. There is flexibility for individual businesses within the overall government framework and there will need to be a process of evaluation to ensure that the measures in place continue to meet the requirements.
The starting point of avoid, eliminate and control means looking at individuals continuing to work from home where possible (the fewer the number of people back in the workplace the lower the risk), and if not look at risk management, which leads to administrative controls – i.e. changing work practices before ending up at PPE. PPE is generally seen as control of last resort but in practice – facemasks, disposable gloves and constant prompts to wash hands for example.
In terms of changing working practices, employers should be thinking about:
- the workspace and how this is laid layout
- how do we make sure it is kept clean and hygienic
- how do we keep people apart
- how can we use toilets, canteens or other shared spaces/facilities safely
- how do we promote and enable higher levels of workplace hygiene
- if we are going to rely on PPE – can we get it, and is it suitable
- what about limiting customer interactions
- will there be enough first aiders on site
- can we manage fire safety, deliveries etc
- what about higher risk workers
- should work tools and equipment be allocated on an individual basis to employees.
These decisions need to be recorded and clearly communicated to staff members.
Data on properties, and people, has never been more important.
Given that compliance is at risk here, such a decision must be made by the Board to ensure good governance. Board approval should be sought and recorded for the approach the organisation is taking.
It is essential that you continue to record your data on compliance and report to your board at all times, and that there is a clear audit trail for issues with access, and if appropriate to the Regulator. Access issues as a result of self-isolation should be readily identifiable.
Operatives need to be provided with the tools to operate in as safe a way as possible:
- Checklist of questions to ascertain occupant’s current health
- Protective equipment (masks, gloves, over clothing)
The Gas Safe website is a useful resource for updates: https://www.gassaferegister.co.uk/help-and-advice/covid-19-advice-and-guidance/
This is something which is certainly on the Government’s radar as there is currently a Bill being heard in Parliament about making MHFAs a legal requirement for workplaces. It is still in the very early stages and therefore it is not clear at this stage what the outcome will be. What is clear is that this is an area which is being taken very seriously and it would not be surprising if measures were put in place regarding MHFAs in the workplace.
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.