How has the law changed?
In part in response to the Covid-19 pandemic, legislation was passed by the government earlier this year which sought to assist companies to trade through the current economic climate. Included within the measures is a degree of protection from compulsory winding up.
The Corporate Insolvency and Governance Act 2020 (The Act), was laid before parliament on 20 May, and became law on 26 June. It is important creditors are aware of what changes have been implemented and the potential and impact which it may have upon debt recovery action you may be considering or have already commenced.
The main part of the Act affecting creditors is the temporary restriction on presentation of winding up petitions and the factors that the Court has to take into account when deciding whether to wind up a company.
On Thursday 24 September 2020 the government passed a further statutory instrument which extended the operation of these restrictions. As a result, the measures which were due to expire on Wednesday 30 September 2020 have now been extended until 31 December 2020.
A key point to note is that the Act has retrospective effect so any pending petitions presented after 27 April will be affected, along with any winding up orders made after that date.
The Act has introduced the following restrictions:
- A petition cannot be presented by a creditor during the period of 27 April 2020 and 31 December 2020 unless the creditor has reasonable grounds to believe that (a) coronavirus has not had a financial effect on the debtor, or (b) the debtor would have been unable to pay its debts even if coronavirus had not had a financial effect on the debtor;
- A petition cannot be presented after 27 April 2020 if it is based on a unsatisfied statutory demand served between 1 March 2020 until 31 December 2020;
- When deciding whether to make a winding up order the Court will need to be satisfied that the grounds giving rise to the petition would have arisen even if Covid-19 did not have a financial effect on the debtor;
- All winding up orders made between the 27 April and 31 December will automatically be void (that is, of no legal effect) unless the Court would have made the winding up order if the new law was in force at the time the order was made.
Related FAQs
Overall it is our experience that the Courts are quickly adapting in the context of the Coronavirus epidemic and making pragmatic decisions. The Judges seem live to the difficulties currently been faced by practitioners dealing with litigation and they are applying the new guidance.
The Courts are also mindful of pressures on NHS frontline staff and are taking steps not to put additional pressures on them at this time, including in our experience vacating an imminent Trial.
Arrangements for end point assessments can be modified or rescheduled. End point assessment organisations should engage with External Quality Assurance Providers to agree arrangements for the end point assessments where face-to-face assessments are being modified. Where rescheduling is required due to Covid-19 issues and there is a specified time limit for the ESA post gateway, a further pause of 12 weeks is allowable. This should be recorded by the training provider in the ILR.
- Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
- Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
- Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
- The ability to get people on site to undertake material operations
In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.
If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.
Again, the primary point must be that an open dialogue is held with that individual to understand their concerns and to properly consider the impact that not wearing PPE will have on their abilities to undertake their duties. Consideration must be given as to whether there are any parts of their duties that they can undertake and whether they can remain in their role. Engage with the individual to ensure that you understand their point of view. What other duties can they do if they cannot do fulfil all the duties of their role?
It would be prudent to take legal advice early in relation to any issue you foresee in performing a contract. This will allow you to:
- Ensure that initial contact with your counterparty is framed in the correct way
- Ensure that any variations are fully documented so that both parties are fully protected