Skip to content

What is a pre-nuptial agreement?

A pre-nuptial agreement is a legal agreement made between two individuals before they marry. A pre-civil partnership agreement (or a pre-registration agreement) is a legal agreement made between two individuals who are planning to become civil partners. These agreements work in the same way as pre-nuptial agreements.

The pre-nuptial agreement usually sets out how the couple wish their assets to be divided between them if they later separate or divorce. Some agreements also detail how the couple currently arrange their finances and how they will arrange their finances during the marriage or civil partnership.

A pre-nuptial agreement can provide the benefits of transparency in relation to financial affairs, certainty as to how assets would be divided if the parties separate or divorce and protection for assets (such as inherited wealth or pre-marital property) from a later financial claim.

Pre-nuptial agreements therefore reduce the risk of there being uncertain, emotionally draining and financially costly court proceedings if the marriage does break down in the future.

If you believe that you may require a pre-nuptial agreement or have any questions about these agreements you should seek legal advice from one of our specialist matrimonial solicitors.

Related FAQs

My planning permission is due to expire, can I extend the period for implementation?

The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.

The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.

The Act includes similar provisions in relation to both detailed and outline planning permissions.

What happens if that means a particular service might need to close?

Ultimately closing a service will be a decision that is taken at the highest level and that decision will depend on risk appetite.  Often these types of higher risk are mitigated by way of insurance but that still depends on an insurer being willing to accept that risk. This decision will depend on accepting a known risk and its consequences.

VIDEO EXPLAINER: Alternatives to redundancy – how to flex your workforce after furlough

This free Getting back to business webinar was held on Wednesday 6th May. On this video, employment partner Paul Scope and associate Flora Mewies looked at your options if you need to flex your employee resource or reduce cost without reducing headcount. This may apply across the business or to particular functions. They discussed a range of options when the furlough scheme comes to an end, including: lay off, short time working, reduced hours, reduced pay and other ways to be flexible.

They also discussed the pros and cons of each option, and cover what you will need to undertake with each of these routes.

How might the transition to a "new normal" impact on contracts?

The workplace will not revert to its pre-Covid-19 state overnight, with social distancing in the work place likely to remain in place for quite some time to come.

This could mean that businesses will need to think carefully about how their capacity will be impacted, and how this will affect their ability to perform contractual obligations.

For example, if a business has an outsourcing contract under which it has to perform a business process, or produce a particular output, will it be able to comply with contractual performance standards whilst social distancing is still in place? In the context of a manufacturing business, what will be the impact on production schedules and delivery dates? There might also be an impact on operating costs, for example if processes are changed and additional shifts are introduced – can these additional costs be sustained?

Businesses need to plan a safe system of work for their employees to ensure they comply with Health and Safety legislation, but they also need to consider how this will impact on their ability to perform pre-existing contractual obligations. Ultimately, contractual arrangements with customers might need to remain on a revised footing for a number of months.

Getting to a point where agreement is reached on allocation of additional costs and/or changes to key elements of a contract such as scope of work, performance standards and delivery date will require co-operation between contracting parties. Again, it is important that any variations that are agreed are recorded properly and follow the required contractual procedures.

Do the usual publicity requirements for planning applications still apply?

The Government has introduced new regulations, which took effect on 14 May 2020, to relax the publicity requirements in respect of planning applications.

Planning applications are usually required to be publicised by way of site notices and local newspaper notices and applications are to be made available for public inspection. The Government has recognised that these actions may not always be possible in accordance with social distancing guidelines and in order that Councils do not delay applications as a result of an inability to comply with the publicity requirements, the Government has relaxed the requirements.

A Local Planning Authority is now required to “take reasonable steps” to publicise a planning application, which may be through use of online newspapers, social media, or other electronic measures. What is considered reasonable will depend upon the circumstances of an individual application and will be proportionate to the scale and impact of the development. A large development that has previously generated significant interest will require more steps to bring the application to the attention of all of those with an interest than a householder application. The guidance emphasises the role of the publicity requirements, namely to enable those with an interest to make representations and to effectively participate in the decision making process and therefore community engagement remains key. It is recommended that the officer’s report refers to the steps taken where a Council has relied upon the temporary publicity arrangements.

The requirement to make planning applications available for public inspection has also been temporarily suspended providing that the applications are available for online inspection. In reality most LPAs already provide such an online facility. Where individuals are unable to access an application online LPAs should make alternative arrangements, for example providing information over the phone or providing a hard copy set of documents by post.

The regulations however only amend the statutory publicity requirements. In addition to these, all LPAs are required to have a Statement of Community Involvement which may provide for additional publicity requirements and the LPA will be bound by these regardless of the temporary relaxation of any statutory requirements. Where a Statement of Community Involvement does go beyond the statutory requirements, the Government guidance suggests that LPAs update these to ensure that local communities can continue to be consulted in the current climate.

The regulations are currently due to expire on 31 December 2020.