What is a pre-nuptial agreement?
A pre-nuptial agreement is a legal agreement made between two individuals before they marry. A pre-civil partnership agreement (or a pre-registration agreement) is a legal agreement made between two individuals who are planning to become civil partners. These agreements work in the same way as pre-nuptial agreements.
The pre-nuptial agreement usually sets out how the couple wish their assets to be divided between them if they later separate or divorce. Some agreements also detail how the couple currently arrange their finances and how they will arrange their finances during the marriage or civil partnership.
A pre-nuptial agreement can provide the benefits of transparency in relation to financial affairs, certainty as to how assets would be divided if the parties separate or divorce and protection for assets (such as inherited wealth or pre-marital property) from a later financial claim.
Pre-nuptial agreements therefore reduce the risk of there being uncertain, emotionally draining and financially costly court proceedings if the marriage does break down in the future.
If you believe that you may require a pre-nuptial agreement or have any questions about these agreements you should seek legal advice from one of our specialist matrimonial solicitors.
Related FAQs
The Government’s Corporate Insolvency and Governance Act introduces amendments to the current rules for companies on holding meetings, to address the difficulties companies are facing due to the Covid-19 pandemic.
The new provisions apply to meetings held between 26 March 2020 and 30 September 2020 (referred to as the “Relevant Period”). Subsequent regulations by the Government can be used to shorten this period or extend by up to 3 months but not past 5 April 2021.
The provisions will have retrospective effect, so meetings that were held after 26 March 2020 that may not have met the usual legal requirements due to lockdown, will be validated under these new provisions. These provisions under the Act make amends to relevant legislation and override a company’s articles of association.
For general meetings and certain other meetings of companies, the Act states that:
- The meeting need not be held in any particular place;
- The meeting may be held, and any votes may be cast, by electronic means or other means;
- The meeting may be held without anyone being in the same place
- Persons attending the meeting no longer have the following rights: the right to attend in person, the right to participate in the meeting other than by voting, or the right to vote by particular means.
The aim of these changes is to facilitate virtual meetings, and remove the need for a physical venue.
Where a company was required to hold its AGM between 26 March and 30 September 2020, it can be held at any time before 30 September 2020. The Secretary of State has the power to make regulations to further extend the deadline.
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
The immediate impact is accounting for payroll purposes for the additional cost of 13.8% employers NIC’s and 0.5% apprenticeship levy on top of the payment to the contactor’s PSC.
Secondary NIC’s cannot be recovered from payments due to employees and the same applies under the new IR35 regime. However, new terms can be agreed with reduced level of fees to reflect this additional cost.
The obvious option to reduce the cost of your workforce is redundancy. However, that also reduces the number of employees and therefore your capacity.
If the duties are so fundamentally different from their contracted role, then yes. For example, if you are asking a frontline clinical member of staff to undertake administrative tasks in another area, then this will be a fundamental change to their terms and conditions for which you need their consent.
If there is a minor alteration to their duties, or the clause within their contract is wide enough to cover their amended duties, then arguably to do not need their consent but best practice would be to obtain their agreement.