What if the status determination is disputed?
You should have in place a dispute resolution procedure that sets out the appeal process or contractors or the agency as appropriate. You must respond to an appeal within 45 days.
If the status determination is disputed you should consider the contractor or agency’s reasons objections. You must consider if the original determination is to be maintained and give reasons for this. Or a new determination with reasons can be provided if appropriate.
Records of disputed determinations and the outcome of any appeal should be kept.
Related FAQs
A quicker and more cost-effective option may be the involvement of the police given their recent allocation of emergency powers to disperse, fine or even arrest persons who flout these rules. Nevertheless, it appears that the Court is willing to support housing providers in their efforts to tackle anti-social behaviour during this time.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
Yes. You can continue to fully furlough employees until 30 September 2021 (but from between 1 August 2020 and 31 December 2020 and from 1 July 2021 you need to contribute to the cost). If on full-time furlough, employees continue not to be able to undertake any work for you. As before, they can undertake training, or volunteer or work for another employer or organisation (if contractually allowed).
The financial implications of having to repay all deposits and advance payments could be very serious for some businesses. As an alternative to a refund, many are offering customers the opportunity to re-book at a later date, or a voucher that can be redeemed against a subsequent booking.
The CMA’s view on this practice is that consumers can in many situations be offered alternatives of this type, but they should not be “misled or pressured” into accepting this. Their view is that a refund should be an option that is just as clearly and easily available. The CMA also points out that any restrictions that apply to credits, vouchers, re-booking or re-scheduling, such as the period in which credits must be used or services re-booked, must also be fair and made clear to consumers.
The full CMA guidance re “The Coronavirus (Covid-19) pandemic, consumer contracts, cancellation and refunds” can be found here.