What if the contractor is supplied by an agency?
As mentioned earlier, if an agency is involved you must send them a copy of the status determination statement for each contractor, and they will also have the right to dispute the outcome.
If the agency pays the contractor, they will be responsible for the operation of PAYE and NIC’s deductions and any apprenticeship levy. The agency may try to recover these costs from the end user client.
If workers are supplied by an agency or umbrella company and are already treated as employees by the agency, they will remain unaffected by IR35.
Related FAQs
Partners Damien Charlton and Jane Garvin look at the provisions of the Bill which impact on a supplier’s rights under a contract when their customer enters an insolvency procedure. They also outline other changes to insolvency procedures that the new law will introduce.
This webinar is part of a series designed for in-house lawyers. If you would like to register to receive invitations to future events for in-house legal counsel, please email damien.charlton@wardhadaway.com.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
- Trusts should allow for telephone advice rather than face-to-face review from critical care when clinically appropriate.
- Hospitals should discuss the sharing of resources and the transfer of patients between units, including units in other hospitals, to ensure the best use of critical care within the NHS.
Please note, the above is intended to provide a summary of the key recommendations which emerge from this guidance. Access to the full guidance can be found here.
- Delays in preparing and submitting applications to comply with pre-commencement conditions. In this respect there can be lengthy timescales gathering evidence to support applications to comply with pre-commencement conditions, ecology, contamination and archaeology are examples of matters which can require significant periods of survey work
- Following on from the above the ability to get required experts on the site necessary to undertake the required survey work
- Delays in the determination of applications to comply with pre-commencement conditions. In this respect whilst there are deemed discharge provisions/procedures concerning certain matters, the provisions cannot be used to discharge all types of conditions
- The ability to get people on site to undertake material operations
In the circumstances, it is advisable to start considering the implementation of the planning permission early and the earlier the better. Under current legislation whilst it is possible to vary conditions, albeit potentially leading to wider issues, it is not possible to extend the life of a planning permission meaning that lawful implementation is essential to avoid the loss of that permission.
If a planning permission is lost, amongst other things it may not be granted again or may not be granted on similar terms. In the circumstances, it is advisable to seek advice given the specific facts of the case to minimise the risk of a planning permission not being lawfully implemented and expiring.
During the COVID-19 global pandemic, trials and hearings have been mostly conducted over Skype for Business and various other online platforms. Looking forward to the future, what we have experienced during the lock-down may continue and we believe will make litigation a more streamlined, user friendly experience for litigants.
One example of a regime which has been introduced is hybrid trials for lower value claims. Hybrid trials allow for parties and their witnesses to be linked into the court room by video link, whilst the judge and advocates are present in court. This makes it easier and frees up more time for witnesses, which would otherwise be spent in travel and waiting time, especially for those with other commitments.
With hybrid trials, clients still get a full legal experience and the judge will still apply normal legal principles during the trial. The procedure for the case is the same, both leading up to the trial or hearing and during the case itself; except without the need to physically attend court. It may also mean that there will be less of a backlog arising from the current crisis with cases continuing to be heard, allowing for matters to be listed earlier and a quicker outcome for the parties involved.
The shift to the use of online platforms may prove more practical for all those involved in legal matters. Interim hearings can be heard remotely resulting in a time and cost saving for litigants. Even for the final hearing only the legal representatives need to attend court – again resulting in time and cost savings for all concerned.