What do I do if my visa is due to expire but I can’t travel?
If your visa has expired or will do before you are able to safely leave the UK, you can apply for “Exceptional Indemnity” by contacting the Coronavirus Immigration Team. You will need to provide evidence as to why you cannot leave, which could include a positive Covid-19 test or evidence of being unable to make travel arrangements to leave the UK in time.
You should note that “Exceptional Indemnity” does not extend your leave, but temporarily protects you from adverse action being made against you as result of overstaying your visa.
Related FAQs
With the outbreak of coronavirus leading to a requirement for more employees to be working remotely, especially following Government advice that all non-essential travel including to and from work should be avoided, there has been an increased requirement for businesses to be more flexible in their approach to signing contracts.
The traditional approach has been for contracts to be printed and signed with a “wet ink” signature. However, this is not a strict legal requirement in the majority of circumstances and contracts can be formed without this degree of formality. English law recognises that contracts can be formed by electronic means – including the exchange of emails or the typing of a name into a document to signify agreement to it.
Whilst this approach offers a lot of flexibility, more sophisticated electronic signature tools are recommended for important documents, to enable the identity of the signatory to be validated and reduce the possibility of fraud.
If businesses are considering changing their contracting processes because of coronavirus, or because of a general shift towards paperless working, it is important to ensure that proper approval processes remain in place, and to consider whether a software tool should be used to complement them. Systems such as DocuSign are widely used.
There also remain some situations where legal advice is recommended before relying on an electronic signature:
- Where the other party is abroad – as local laws that are different from English law might apply
- If executing a deed – the law requires certain types of document to be executed as a deed (for example, transfers of land and powers of attorney), and the issues around electronic signature and witnessing are more complicated here
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.
Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.
Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.
New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.
For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.
Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.
For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.
You must only make a report under RIDDOR (The Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013) when:
- An unintended incident at work has led to someone’s possible or actual exposure to coronavirus. This must be reported as a dangerous occurrence
- A worker has been diagnosed as having COVID 19 and there is reasonable evidence that it was caused by exposure at work. This must be reported as a case of disease
- A worker dies as a result of occupational exposure to coronavirus.