What do I do if I can’t travel to the UK to activate my visa?
If your 30-day visa to travel to the UK (vignette) has expired or is about to, you can request a replacement free of charge until the end of 2020 by contacting the Coronavirus Immigration Help Centre. This can be granted with new and extended validity dates to allow travel once you are able to.
Related FAQs
A reduction in hours or salary or changes to hours or patterns of work is a contractual change – you can’t just impose it without significant risk. The same applies for lay-off or short-time working where there is no existing contractual right to impose these.
In summary, the process that an employer should follow to implement these measures is as follows:
- Communicate the Company’s position clearly and the urgent need to achieve temporary cost-saving to ensure the ongoing financial viability of the organisation
- Explain the proposed changes in detail and seek the employee’s agreement, and
- Record the agreed changes in a letter which is counter-signed by the employee.
If employees will not agree then employers will be at substantial risk of claims for unlawful deduction of wages, breach of contract and/or constructive unfair dismissal if they seek to impose these changes unilaterally. Employers should be mindful that this approach is likely to cause significant employee relations issues and dissatisfaction if only some employees agree to a reduction in pay. Employers should have a clear strategy for what their approach will be if this is the case – for example, they may wish to instead explore a different measure such as redundancies. This may form part of the employer’s communication when explaining the reason for the changes and seeking the employee’s agreement.
Unions: Employers should also be aware that where there is a recognised trade union in respect of any part of the workforce which is being asked to agree to a change to terms and conditions, the recognition agreement or collective agreement will require the employer to consult and/or negotiate with the trade union in the first instance.
Collective consultation: Where 20 or more dismissals are proposed at one establishment in any 90-day period, there are stringent collective consultation rules which apply (regardless of whether the employees have two years’ service or not). All dismissals count towards this total unless the dismissal is “not related to the individual concerned” – therefore dismissals for things such as conduct or capability do not count, but most other dismissals will count. This will include where you are imposing changes to the contract such as reduced hours or pay.
The rules on collective consultation set out a prescriptive and time-consuming process which must be followed, and minimum timescales before any redundancies can take effect. The cost of any claims relating to failure to follow collective consultation requirements are substantial, and specific advice should therefore always be sought before seeking to implement collective redundancies. We will be publishing further guidance on this on the Hub shortly.
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?
Parties still need to comply with the various Protocols that apply and will be expected to exchange information in the usual way. Court proceedings can be issued electronically.
Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.
The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.
New guidance has been published alongside the Act and is available here
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs