Skip to content

What are the standard holiday rules?

Under usual rules, workers are entitled to a minimum of 28 days holiday including bank holidays, each year. Except in limited circumstances, it cannot be carried between leave years meaning that workers lose their holiday if they do not take it.

The government passed emergency legislation relaxing the carry-over of the 20 days leave entitlement provided under EU law. Where it is not reasonably practicable for an employee to take leave in the relevant leave year as a result of the effects of the coronavirus then they could be entitled to carry over the untaken leave into the next year.

Related FAQs

Are there specific examples given?

The guidance gives numerous examples of the types of performance adjustment which parties should consider. For example this includes:

  • Varying deadlines (e.g. for performance or payment)
  • Varying compensation (e.g. to recognise increased costs)
  • Varying the nature of performance (e.g. allowing substitute goods, allowing pert delivery of services)

The guidance also encourages a reasonable approach to enforcement, which might encourage delaying issuing formal proceedings, increased use of mediation or providing more information to the other party than would be volunteered under normal circumstances.

Who do the Procurement Policy Notes (PPN) apply to?

All three of the PPNs are effective immediately and apply to the following Contracting Authorities:

  • Central Government Departments
  • Executive agencies
  • Non-departmental public bodies
  • Local authorities
  • NHS bodies
  • The wider public sector

In regards to PPN03/20, those in scope organisations that do not currently use procurement cards are advised to immediately put in place arrangements using the relevant Crown Commercial Service Agreement (Lot 2 of RM3828 Payment Solutions).

Is the current pandemic an event which will allow me to argue that the lease has been ‘frustrated’?

This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.

This is not something that can be demonstrated easily.

There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.

The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.

Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.

What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases

The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:

  • The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
  • How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
  • Whether the definition of higher risk buildings is correct, or will require some refinement.

The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.

What are the minimum consultation time limits?

Where an employer is proposing to dismiss:

  • 100 or more employees at one establishment within a 90-day period, consultation must begin at least 45 days before the first dismissal takes effect
  • Between 20 and 99 employees within a 90-day period, consultation must begin at least 30 days before the first dismissal takes effect
  • If you are proposing to dismiss less than 20 employees then there are no minimum time limits but you must adhere to a fair process which will involve individual consultation and providing the employee with a right of an appeal