What are the responsibilities of employers under the coronavirus Test and Trace scheme?
The Government has produced workplace guidance for employers, setting out 2 key messages for employers:
- Continue to make workplaces as safe as possible; and
- Encourage workers to heed any notifications to self-isolate and to support them while they are require to isolate
Government guidance can be accessed here: How it works (an overview) and Workplace guidance for employers.
Related FAQs
Civil Court listing priorities, last updated by HMCTS on 24 April 2020, categorise the Court’s work into the following:
Priority 1 – work that must be done: this includes any applications in cases listed for trial in the next 3 months, any applications where there is a substantial hearing listed in the next month, all multi-track hearings where parties agree that it is urgent (subject to triage).
Priority 2 – work that could be done: Infant and Protected Party approvals, Applications for interim payments in multi-track / personal injury / clinical negligence cases, Applications to set aside Judgment in default, Preliminary Assessment of costs.
The full guidance can be found at:
The Government expects the use of bespoke contractual documents to implement temporary arrangements relating to your PFI contracts.
With time and resource precious commodities, focus should be given to documenting:
- The key changes to your PFI requirements
- The temporary nature of the measures
- The requirement for best efforts on behalf of the PFI Contractor
- The importance of continued health and safety measures at all times
There is no minimum period of notice you are required to give employees of their return, but from a good HR practice point of view you should be speaking to your staff and letting them know what the plan is; giving people a reasonable amount of notice of return will allow them to prepare both practically and psychologically.
This is unlikely. Frustration is a doctrine rarely used as a way of getting out of leases. It operates to bring a lease to an early end because of the effect of a supervening event. It is then not a concept readily applicable to a situation where one party is looking to get out of a lease. To be able to argue the doctrine of frustration, you must be able to demonstrate that something unforeseeable has happened that makes it impossible to fulfil the lease and unjust to hold a party to its obligations.
This is not something that can be demonstrated easily.
There was a case in the High Court last year when the doctrine of frustration was looked at in a case involving the European Medical Agency.
The court found that Brexit did not frustrate EMA’s lease. EMA was granted leave to appeal that decision to the Court of Appeal, but unfortunately, the parties settled out of court so the arguments were not tested in the higher court.
Another reason why frustration is likely to fail is an argument that, whilst the current lockdown may force closures to businesses and whilst such closures maybe for a lengthy period, such closures will only be temporary.
If a contract contains a force majeure clause this may become operative due to the coronavirus pandemic and related emergency legislation. Such clauses exist to ensure that if some unforeseen event prevents a party from being able to perform their obligations under a contract, either on time or at all, they will be excused from their obligations and not be held liable for non-performance.
The clause must actually be written into the contract to have effect – a force majeure clause cannot be implied into a contract. Whether it can be relied on by a party will depend on the wording of the clause itself as it may only be applicable in certain limited circumstances.
You should seek legal advice at an early stage if you think that force majeure is relevant, because a number of potentially complex issues must be addressed, many of which will turn upon the exact wording of the force majeure clause in the contract in question:
- Has a force majeure event actually arisen?
- What notification process do you have to follow to rely on the provision?
- What mitigation steps do you have to take?
- What is the effect of the force majeure event – is the contract suspended, or can it be terminated (which might not be what you want)?