What are the NICE protocols around a patient’s ongoing treatment whilst in critical care during the pandemic?
- Start critical care treatment with a clear plan of how the treatment will address the diagnosis and lead to agreed outcomes.
- Review critical care treatment regularly and when the patient’s clinical condition changes.
- Stop critical care treatment when it is no longer considered able to achieve the desired outcomes. Record the decision and the discussion with family, carers and the patient (if possible).
Related FAQs
The Government has produced and published three new Procurement Policy Notes as a direct result of the ever changing Covid-19 environment.
PPN 01/20: Responding to COVID-19
The purpose of PPN 01/20 is to ensure that contracting authorities are able to procure goods, services and works with extreme urgency, to allow them to respond to the pandemic efficiently.
This PPN provides guidance for the following circumstances:
- Direct award due to extreme urgency (regulations 32(2)(c)) (click here to read our article regarding regulation 32)
- Direct award due to an absence of competition or protection of exclusive rights
- Call off from an existing framework agreement or dynamic purchasing system
- Call for competition using a standard procedure with accelerated timescales
- Extending or modifying a contract during its term
PPN 02/20: Supplier relief due to COVID-19
PPN 02/20 focuses predominantly on the supplier to assist in keeping supply chains open and ensuring that suppliers are kept financially sound during these unpredictable times.
This PPN provides guidance for the following circumstances:
- Urgent reviews of contract portfolios and to update suppliers if they believe they are at risk
- Put in place appropriate payment measure to support supplier cash flow
- Where contract payments are based on ‘payment by results’ make payments based on previous invoices
- Ask suppliers to act on a ‘open book’ basis and make cost data available to the contracting authority during this period
- Ensure invoices submitted by suppliers are paid immediately on receipt
PPN 03/20: Use of Procurement Cards
The third guidance note PPN 03/20 relates to the use of procurement cards to increase efficiency and accelerate payment to suppliers.
This PPN provides the following advice and urges organisations to arrange with their procurement card provider to:
- Increase a single transaction limit to £20,000 for key card holders
- Raise monthly limits on spending with procurement cards to £100,000 for key card holders
- Spend on procurement cards each month in excess of £100,000 should be permissible to meet business needs
Although the above advice has been provided, should these limits not be necessary, organisations should seek an appropriate transaction limit or monthly limit.
The PPN also advises that by 30 April 2020, in scope organisations should:
- Ensure that a number of appropriate staff have the authority to use these cards
- Open all relevant categories of spend to enable these cards to be used more widely
The reality of these unprecedented times is that enforcement of health and safety legislation by the HSE (particularly through the criminal courts) in relation to Covid-19 is an extremely unlikely outcome.
The FCA’s test case in the Supreme Court ruled overwhelmingly in favour of policyholders. However, business interruption cover generally has the prerequisite of physical damage or loss to the property (or in some circumstances, the presence of a notifiable disease at the property or within a certain radius of it), to recover losses caused by the interruption to your business. The onus is on insurers to re-assess those claims which are impacted by the Supreme Court’s judgment and to make contact with the policyholders regarding next steps. If you have not already made a claim, in the first instance the terms of any policy should be checked carefully to see whether business interruption cover is provided.
The Construction Leadership Council (with backing from the Government) has issued practical guidance and draft pro-forma documents to enable all parties involved in the construction supply chain to enter into collaborative and open dialogue about applications for extensions of time and additional payment and to minimise potential disputes. The guidance can we downloaded here
The draft letters and notices included in the guidance have been prepared on the basis of the standard JCT Design and Build 2016 and NEC 3/4 Engineering and Construction Contract (Option A) and parties will need to make sure that they are completed/adjusted to comply with their own specific contracts.
The Cabinet Office has also issued a general statement calling on parties to contracts adversely affected by C-19 to act responsibly and fairly and to support national efforts to protect jobs and the economy.
There are four criteria which must be satisfied if an agreement is to be considered exempt:
- It must improve production or distribution, or promoting technical or economic progress – the guidance suggests that cooperation ensuring essential goods and services can be made available to the public, or an important sub-set of the public such as key workers, will satisfy this criterion.
- It must allow consumers a fair share of the resulting benefit – the guidance suggests this will be the case where the action prevents or reduces shortages.
- It must not impose on the undertakings concerned restrictions which are not indispensable to the attainment of the above benefits – the guidance suggests this will be the case where the cooperation is the only reasonable option due to the urgency of the crisis and where the cooperation is temporary in nature.
- It must not afford the undertakings concerned the possibility of eliminating competition – therefore the parties must endeavour to retain competition in respect of the products (in particular price competition).