Skip to content

What are the NICE protocols around a patient’s ongoing treatment whilst in critical care during the pandemic?

  • Start critical care treatment with a clear plan of how the treatment will address the diagnosis and lead to agreed outcomes.
  • Review critical care treatment regularly and when the patient’s clinical condition changes.
  • Stop critical care treatment when it is no longer considered able to achieve the desired outcomes. Record the decision and the discussion with family, carers and the patient (if possible).

Related FAQs

Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.

Which properties should I prioritise?

Some organisations are prioritising properties, known to be higher risk, such as properties with open flues, or near to the certificate expiry date.

Vulnerable staff and tenants need protection, safe working practices need to be established, and communicated. Organisations should bring forward servicing for people known to be vulnerable – but bearing in mind the guidance as to preserving the annual test date.

What guidance has the Government given in relation to contracts in relation to Covid-19?

On 7 May the Government published guidance on how contracting parties can act responsibly in order to assist the effort to deal with Covid-19. The guidance seeks to persuade contracting parties to act reasonably and recognise the impact of Covid-19 on contractual counterparties. This will continue to be relevant as business begins to emerge from lockdown.

Do you have to collectively consult for the minimum period of time before you can issue notice?

These periods are often mistakenly referred to as minimum lengths of consultation (especially by Trade Unions). That is not correct. Consultation can commence, conclude and notices of dismissal be issued within the 30 and 45 day periods. The expiry of the notice would just have to be outside of those restricted periods.

What perceived gaps do you see in the Building Safety Act 2022 (especially in terms of pending consultations and secondary instruments)?Comments on the value of the Martlet v Mulalley judgment in fire safety cases/unsafe cladding cases

The Act was obviously subject to much debate and criticism as the Bill passed through Parliament. It is difficult to properly assess any gaps until after the necessary secondary legislation has been published and comes into force (along with the remainder of the Act), but some of the likely issues include:

  • The impact on the insurance market, and the (lack of) availability and increased cost of insurance in light of the provisions of the Act
  • How the introduction of retrospective claims will affect the market, both in relation to how parties might go about trying to prove matters which are 30 years old, but also the lack of certainty for those potentially on the receiving end of these claims which they previously had by virtue of the Limitation Act provisions
  • Whether the definition of higher risk buildings is correct, or will require some refinement.

The Martlet v Mulalley case provides some useful observations and clarifications, for example that designers cannot necessarily rely on a ‘lemming’ defence that they were simply doing what others were doing at the time, that ‘waking watch’ costs are generally recoverable, and commentary on certain specific Building Regulations. The judgment however made clear that much of the case turned on its specific facts, so it is useful from the perspective of providing some insight as to how the Courts will deal with cladding disputes in future, rather than setting significant precedents to be followed.