Skip to content

What are the key questions to ask ourselves as a business?

Some examples of the key questions to ask include:

  • Is there still a viable underlying business that is likely to continue beyond the current crisis?
  • What does the revised short to medium cash flow look like and will the company continue to be able to pay its liabilities?
  • Does the company have the support of all of its stakeholders – lenders, shareholders, customers, suppliers and banks – even though the business might be in breach of its own obligations?
  • What measures could (and should) the board put in place to protect creditors, including making sure that exposure to creditors (both collectively and individually) is not increased, assets are not sold at less than value and no creditor is treated more favourably than another?
  • Is there still a reasonable prospect of the business avoiding liquidation or administration?

The key question is always whether accepting the money is in the best interests of creditors as a whole bearing in mind that accepting Government support and continuing to trade might increase the company’s overall liabilities. Directors should be mindful that if the business fails, their decisions during this critical time may be scrutinised and it is therefore important that directors have up-to-date financial information and projections to form the basis of any decisions, take stock, get the right advice and document the decisions that are taken.

Related FAQs

My reserved matters application is due to be submitted, can I delay this?

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 18 of the Act includes provisions for the extension of the date by which a reserved matters application must be submitted where the original date falls between 23 March 2020 and 31 December 2020. Where the original time limit for the submission of reserved matters is on or after 19 August 2020, the relevant conditions will be automatically read as requiring the reserved matters application to be submitted by 1 May 2021.

Where the original time limit for the submission of reserved matters is before 19 August 2020, an application will need to be made to the LPA for an Additional Environmental Approval (“AEA”), which the LPA must determine within 28 days otherwise the approval is deemed to be provided. The purpose of the AEA is to consider whether the environmental assessments carried out at the time of the original outline determination remain valid and up to date, and where that is not the case, the AEA will be refused. In such circumstances a new planning application will be required where an application is now out of time to comply with the original date for submission of reserved matters.

Will there be further measures for self-employed announced?

The Government assured parity for the self-employed but it has since accepted that this would be difficult to achieve. The Association of Independent Professionals and the Self-Employed (IPSE) has worked closely with the Government on implementing the current self-employment income support scheme. IPSE has confirmed that it will continue to work on helping to extend measures to all freelancers in need as a result of Covid-19.

The Government announced an extension to the Self-Employment Income Support Scheme from 1 November 2020.

 

There is a court order in place in relation to access to my child. What should I do?

If there is a court order then this should be complied with, unless you are unable to do so because the parent with whom the child lives is self-isolating, the other parent is self-isolating or the children are showing symptoms of the virus. If you are unable to comply with the court order, the other parent should be notified immediately in writing and proposals put forward for how they can see and speak to their children by telephone, FaceTime, Zoom or some other method.

If any necessary variations to the arrangements cannot be agreed then you should contact us for legal advice.

What is the current guidance relating to Private Finance Initiatives and PF2 Projects in light of coronavirus?

On 2 April 2020, the Government issued guidance relating to Private Finance Initiatives and PF2 Projects. The guidance, which is to be enforced with immediate effect (currently due to stay in place until 30 June 2020), is one of several guidance notes issued to date.

A link to the guidance is set out below:

https://assets.publishing.service.gov.uk/government/uploads/system/uploads/attachment_data/file/877804/2020_04_01_PFI_and_COVID19_final.docx.pdf

Key messages to contracting authorities

  • PFI contractors should very much consider themselves as being part of the public sector response to the current pandemic
  • Covid-19 is not regarded as, and is not to be classified as a force majeure event
  • PFI contractors must ensure that contingency plans are up to date and have been reviewed and discussed with contracting authorities to enable the continuity of full services to respond to the pandemic and maintain vital public services
  • Contracting authorities should work closely with PFI contractors to use all available options to maintain public services during the emergency period
  • Local arrangements should be made where PFI contractors can’t deliver the agreed requirements and performance standards
  • “Best efforts” should be made by all parties for the continuation of service provision
What is happening about court and arbitration hearings?

The courts are seeking to adapt to our new circumstances and have urgently been looking to introduce new ways of working. The courts have been testing out different ways of holding court hearings. The advice is changing almost daily and some courts have been developing local practices. Going forward the court, the parties and their representatives will need to be more proactive about all forthcoming hearings.

Everyone involved in the case is to consider as far ahead as possible how future hearings should best be undertaken and work collaboratively. It will normally be possible for all short, interlocutory, or non-witness, applications to be heard remotely. Some witness cases will also be suitable for remote hearings. The parties just need to ensure that everyone involved can use the technology suggested.

The courts have been looking at and held remote hearings using, non-exhaustively, BT conference call, Skype for Business, court video link, BT MeetMe, Zoom and ordinary telephone call. Bundles for the hearing will be prepared and circulated electronically.

If the hearing cannot be held remotely because the parties do not have the requisite technology or the length of the hearing combined with the number of parties or overseas parties, representatives and/or witnesses make it undesirable to go ahead with a hearing in court at the current time, then it may be that the case will need to be adjourned. We are hearing of trials being adjourned and that they will not be re-listed before at least September.

HMCTS has advised that several priority courts will remain open during the coronavirus pandemic to make sure the justice system continues to operate effectively. It publishes a daily operational update from the courts and they aim to update it by 9am. The link is https://www.gov.uk/guidance/hmcts-daily-operational-summary-on-courts-and-tribunals-during-coronavirus-covid-19-outbreak.

Also, the courts have circulated a civil listing priority list with Priority 1 listing work which must be done and which includes injunctions, any applications in cases listed for trial in the next three months, any applications where there is a substantial hearing listed in the next month and all Multi Track hearings where parties agree that it is urgent.

In the Priority 2 list, which consists of hearings which could be done, are enforcement of trading contracts, trial involving the survival of a business or the insolvency of an individual, small and fast track trials where the parties say they are urgent, and appeal in these kinds of cases.

Similarly, in arbitration proceedings, the parties and arbitrators are being encouraged to utilise technology to make sure that hearings take place. We have heard of Zoom being used very successfully for multi-party proceedings.