What agreements will the CMA choose not to take enforcement action in respect of?
CMA guidance suggests that it will not take enforcement action in respect of agreements which:
- Are appropriate and necessary to avoid a shortage, or ensure security, of supply
- Are clearly in the public interest
- Contribute to the benefit or wellbeing of consumers
- Deal with critical issues that arise as a result of the Covid-19 pandemic
- Last no longer than is necessary to deal with these critical issues
Related FAQs
If your 30-day visa to travel to the UK (vignette) has expired or is about to, you can request a replacement free of charge until the end of 2020 by contacting the Coronavirus Immigration Help Centre. This can be granted with new and extended validity dates to allow travel once you are able to.
It is. If you assess a risk and identify a control measure then fail to deploy it, then you are breaching your legal duties under HASWA and potentially committing a criminal offence. So if you decide for example that N95 respirators have to be used by everyone, you have a duty to provide them.
So the short answer is yes.
Arrangements for end point assessments can be modified or rescheduled. End point assessment organisations should engage with External Quality Assurance Providers to agree arrangements for the end point assessments where face-to-face assessments are being modified. Where rescheduling is required due to Covid-19 issues and there is a specified time limit for the ESA post gateway, a further pause of 12 weeks is allowable. This should be recorded by the training provider in the ILR.
It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved. To be in the best possible position, it is worth considering the following at the outset of any project:
- Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
- Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
- Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
- Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
- Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
- Project bank accounts and escrow accounts can also provide some further assurances for the parties involved
The law says that if after assessing a risk and considering all the control measures available to you, you cannot undertake a task safely – then you should not undertake the task.
If that means taking BAME workers out of higher risk frontline work, that is what will have to be done.
Beware of workers saying “we’ll accept the risk” – it does not protect you against regulatory/enforcement action or civil claims.