Skip to content

VIDEO: SRA Standards and Regulations

Damien Charlton, Julie Huntingdon and Chris Hugill look at the SRA Standards and Regulations (STaRS) for solicitors which came into effect late 2019, and represented a whole new regulatory landscape for the legal profession. The enhanced reporting and transparency obligations have an important impact on in-house practice, so this webinar gives you the opportunity to reflect on how the new rules impact on in-house lawyers, in both your professional and personal lives.

This webinar is part of a series designed for in-house lawyers. If you would like to register to receive invitations to future events for in-house legal counsel, please email damien.charlton@wardhadaway.com.

Related FAQs

Can construction work be undertaken outside of any permitted hours to make up for site closures?

Many planning permissions contain a condition restricting the hours within which a developer can carry out construction work or are subject to an approved construction management plan setting out the permitted construction hours.

The Business and Planning Act 2020 entered the statute books on 22 July 2020. Section 16 of the Act incorporates a new S.74B into the Town and Country Planning Act 1990. The effect is that any condition/approved document which limits construction hours on a site could be amended through an application to the local planning authority. The application to the local planning authority must set out the date on which the proposed extension to construction hours shall cease (such date being no later than 1 April 2021, after which the original conditions over construction hours will resume). The local planning authority must determine the application within 14 days (beginning with the day after the application was submitted) otherwise there is deemed approval.

New guidance has been published alongside the Act and is available here

How do I guard against contractor insolvency in the construction industry?

It is almost impossible to completely guard against the risks associated with contractor insolvency, but there are some steps which can assist in mitigating and managing the risks involved.   To be in the best possible position, it is worth considering the following at the outset of any project:

  • Check the contractor’s financial position – particularly the specific company which will enter into the building contract, as the employer’s rights will be against this company rather than the business as a whole
  • Take legal advice to ensure that the building contract is properly drafted with appropriate provisions to deal with an insolvency event
  • Consider requiring a performance bond and/or parent company guarantee (each serve slightly different purposes)
  • Obtain collateral warranties from the consultants and sub-contractors involved, so that there are contractual rights against other parties if the contractor is no longer able to meet claims
  • Consider requiring retention bonds, advance payment bonds or vesting certificates if necessary
  • Project bank accounts and escrow accounts can also provide some further assurances for the parties involved
Can I renegotiate a s106 agreement if the viability on my site has changed as a result of the current climate?

The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.

In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.

The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.

Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.

What are the NICE protocols around a patient’s ongoing treatment whilst in critical care during the pandemic?
  • Start critical care treatment with a clear plan of how the treatment will address the diagnosis and lead to agreed outcomes.
  • Review critical care treatment regularly and when the patient’s clinical condition changes.
  • Stop critical care treatment when it is no longer considered able to achieve the desired outcomes. Record the decision and the discussion with family, carers and the patient (if possible).
What should payroll look out for if the Government's Coronavirus Job Retention Scheme is used?
  • It is important to have a clear paper trail for any agreed reduction in salary, and hence any reduction in the amount of contributions. However, the contribution rates (as opposed to the amounts) should be the same as normal, and hence all processes and software should function as per normal and, amongst other things, remain compliant with auto-enrolment employer duties.
  • However, if the period of affected contributions does not overlap precisely with the period of reduced salary, for example because of different cut-off dates, there may well be instances of non-compliance with auto-enrolment employer duties at the beginning as well as at the end of the period covered by the Coronavirus Job Retention Scheme.
  • Accordingly, where an employer takes advantage of the Coronavirus Job Retention Scheme, good communication with the persons responsible for pensions administration and detailed record-keeping are essential to prevent non-compliances in the short-term and confusion in the long term.