The National Lockdown Guidance states that anyone who is clinically extremely vulnerable should not attend work. What options do I have if an employee is in the clinical extremely vulnerable category but cannot do their job at home?
The now defunct Guidance for the Tier system suggested that the clinically extremely vulnerable would be treated in the same way as those who were shielding in Lockdown 1. This means that anyone who is clinically extremely vulnerable and cannot work remotely, will be entitled to SSP. These employees should receive a letter confirming that they are deemed to be clinically extremely vulnerable/shielding and you should ask for a copy of it as evidence to support a claim for SSP. It is likely that the Lockdown 3 Guidance will be the same.
You could also furlough an employee in the clinically extremely vulnerable category. Again we do not anticipate this changing.
Related FAQs
Payments of the Community Infrastructure Levy (“CIL”) are tied to commencement of development, and where an instalment policy is in place, the instalments are usually tied to periods of time following commencement rather than build out rates. Therefore where a development has commenced, payments of CIL are likely to fall due in respect of a site notwithstanding that the site may have temporarily closed or build out rates have slowed.
New regulations now in force, provide some additional relief for those developers with an annual turnover of £45 million or less. Such relief will allow the Council to defer payments, disapply late interest charges, and refund late interest charges that have already been levied since 21 March 2020.
For those developers that cannot benefit from the new provisions, unless a Council has adopted an exceptional circumstances relief policy the regulations do not provide for any relief to be provided in instances where payment of CIL will create viability issues. Most Councils have not adopted such a policy, and in those circumstances the CIL liability will remain due in accordance with the payment schedule on the demand notice.
Councils are at liberty to amend their instalment policies in accordance with their own internal procedures, and the Government is encouraging Councils to explore this option to provide some relief to developers. However this will only assist in respect of any prospective instalments where the development commences after the new instalment policy has been adopted.
For those developers whose annual turnover exceeds £45 million, the Government seems to be taking the view that such developers can afford their CIL liabilities regardless of the current climate. The only concession the Government has proposed is to encourage Councils to make use of the existing discretion they have in respect of the imposition of surcharges for late payments.
Most rent suspension clauses in commercial property leases are unlikely to come to the assistance of the tenant. These clauses normally apply only where the premises has suffered substantial physical damage and are, as a consequence, incapable of being occupied, used or accessed. The coronavirus pandemic does not involve any physical damage to a property, loss from the crisis will be purely financial. Such losses then will not be covered by the landlord’s buildings insurance policy in a way that will allow a tenant to claim rent suspension.
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.
As the project progresses, it is important to continually monitor the contractor’s performance. Any one or more of the items below can be early warning signs that the contractor is in financial difficulty, and that further actions may be necessary:
- Decrease in labour or contractor’s personnel on site, and/or rapid turnover of contractor’s personnel
- Slowdown in progress on site
- Plant, equipment or materials suddenly disappearing from site for no apparent reason – unpaid subcontractors may unilaterally decide to remove items from site regardless of their contractual rights to do so
- An increasing number of defects and reduction in the quality of the contractor’s work
- The contractor seeking changes in the payment arrangements, and in particular early payments
- The contractor making spurious claims or contra charges
- The contractor seeking assignment of its benefit of the building contract
- Late filing of accounts by the contractor at Companies House
- Unsatisfied court judgements against the contractor
- Subcontractors and suppliers not being paid or being paid late
- Rumours in the press, in the industry, on site or elsewhere regarding the solvency of the contractor
- Unusual visits to site, for example from the contractor’s senior management or other personnel who had not previously been present or are not expected to be present
- Increasingly aggressive behaviour by the contractor
- The contractor’s parent company or another company within the contractor’s group displaying any of the above signs
The Cabinet Office has published a useful Procurement Policy Note (“PPN”) on relief available to suppliers due to Covid-19 (available here). In brief, you should not be penalised by a public sector body, if, in the current circumstances, you are unable to comply (fully or partly) with your contractual obligations. Public sector bodies are expected to work with suppliers and, if appropriate, provide relief against current contractual terms. This is in order to maintain business and service continuity and avoid claims being accepted for other forms of contractual relief, such as the occurrence of a force majeure event.
The types of relief that may be available to suppliers to the public sector will depend on the existing contracts in place. Some contracts may have a payments by result mechanism, whereas others may be based on certain key performance indicators (KPIs) being met. Other contracts may not include any such mechanisms and therefore it will be a matter for discussion between suppliers and the public sector body.
The PPN provides that, rather than a supplier seeking to invoke a clause that would permit the supplier to suspend performance of its obligations (such as a force majeure clause), public sector bodies should first work with the supplier to amend or vary the contract. Any changes should be limited to the particular circumstances and considered on a case-by-case basis. Changes could include:
- Amending the contract requirements
- Varying timings of deliveries
- Relaxing KPIs or service levels
- Extending time for performance (e.g. revising a contract delivery plan), and/or
- Preventing the public sector from exercising any rights or remedies against the supplier for non-performance (e.g. liquidated damages or termination rights).
These should only be temporary variations and the contract should return to the original terms once the impact of the Covid-19 outbreak on the contract has ended. Discussions with the public sector body about any changes that are agreed should be documented, in a variation signed by both parties.
A public sector may also need to take account of regulation 72 of the Public Contract Regulations 2015, to ensure that any changes to a contract (even of a temporary nature) do not trigger a requirement to conduct a new tender process. Whilst this may be unlikely to be the case with temporary variations, suppliers should still bear this in mind when discussing any changes to a contract with a public sector body.
If you are a supplier to a public sector body and you are currently struggling to meet your contractual obligations, we recommend that you take legal advice as to whether it might be possible to take advantage of the flexible approach that the PPN requires public sector bodies to adopt – it could be that you can avoid service credits or other financial deductions, or the need to serve formal notices such as “force majeure” or other relief notices.