The employee I need to consider suspending is a doctor – do I have to follow MHPS
Yes probably in our opinion, even if you are not considering taking any formal action against them. Ultimately if a doctor is suspended this could be considered as causing them reputational damage and it therefore is correct that they are afforded the protections (in particular in relation to keeping exclusion/suspension under review) of MHPS. Under Part V of MHPS there is provision for excluding practitioners if they are a danger to patients and they refuse to recognise it or if they refuse to co-operate. It doesn’t refer to a particular risk for the practitioner themselves, but it would appear logical that it would apply.
Related FAQs
Yes. The Town and Country Planning (General Permitted Development) (Coronavirus) (England) (Amendment) Order 2020 came into force on 9 April 2020 giving permitted development rights for emergency development. The permitted development right is available to local authorities and health service bodies (as defined) on land owned, leased, occupied or maintained by it for the purposes of:
- Preventing an emergency
- Reducing, controlling or mitigating the effects of an emergency
- Taking other action in connection with an emergency
It could cover, for example, the temporary change of use of buildings into a Nightingale Hospital or the establishment of a testing centre.
The permitted development right is not permitted in certain instances and is subject to a number of conditions including the notification of the local planning authority and the cessation of the use before 31 December 2020.
Further detail of the permitted development right is available at the link below.
Those who are eligible will be contacted directly by HMRC based on tax returns they have received. If you are eligible you will be asked to fill out an online application. HMRC will pay applicants directly.
The Government acknowledges that there may need to be some flexibility to enable developers to meet any existing s106 obligations, in particular financial contributions, during the current health crisis and in recent guidance it encourages Councils “to consider whether it would be appropriate to allow the developer to defer delivery”. However, the Government considers that the existing arrangements for varying a section 106 agreement by way of a deed are sufficient and will not be legislating for any additional temporary mechanisms.
In the absence of any formal variation, the Government does however advise Councils to take a “pragmatic and proportionate approach” to enforcement of planning obligations at the current time.
The Government’s advice does not refer to concerns over the quantum of any planning obligations but is concerned only with the timing for delivery. However, the viability behind many sites is likely to change as a result of temporary site closures, or the availability of construction materials and labour once sites can re-open. Where there is already a s106 agreement in place, a developer may wish to renegotiate their position on the basis that certain planning obligations are no longer affordable.
Where a s106 agreement was entered into longer than 5 years ago, an application can be made to the Council to formally vary a planning obligation that is now “without purpose”. Any refusals can be appealed to the Secretary of State.
Where a s106 agreement was entered into within the last 5 years, the agreement can only be modified with the agreement of the Council. The ability to renegotiate a s106 agreement will therefore come down to the willingness of the Council to accept the revised viability position. Where Councils are willing to consider this, a robust viability assessment agreed with the Council is likely to be needed.
- On admission to critical care, the risks, benefits and likely outcomes of the different treatment options should be discussed with patients, families and carers so they can make informed decisions about their treatment wherever possible.
- A member of the critical care team should be involved in these discussions whenever the patient or team needs advice about critical care to make decisions about treatment.
The courts are seeking to adapt to our new circumstances and have urgently been looking to introduce new ways of working. The courts have been testing out different ways of holding court hearings. The advice is changing almost daily and some courts have been developing local practices. Going forward the court, the parties and their representatives will need to be more proactive about all forthcoming hearings.
Everyone involved in the case is to consider as far ahead as possible how future hearings should best be undertaken and work collaboratively. It will normally be possible for all short, interlocutory, or non-witness, applications to be heard remotely. Some witness cases will also be suitable for remote hearings. The parties just need to ensure that everyone involved can use the technology suggested.
The courts have been looking at and held remote hearings using, non-exhaustively, BT conference call, Skype for Business, court video link, BT MeetMe, Zoom and ordinary telephone call. Bundles for the hearing will be prepared and circulated electronically.
If the hearing cannot be held remotely because the parties do not have the requisite technology or the length of the hearing combined with the number of parties or overseas parties, representatives and/or witnesses make it undesirable to go ahead with a hearing in court at the current time, then it may be that the case will need to be adjourned. We are hearing of trials being adjourned and that they will not be re-listed before at least September.
HMCTS has advised that several priority courts will remain open during the coronavirus pandemic to make sure the justice system continues to operate effectively. It publishes a daily operational update from the courts and they aim to update it by 9am. The link is https://www.gov.uk/guidance/hmcts-daily-operational-summary-on-courts-and-tribunals-during-coronavirus-covid-19-outbreak.
Also, the courts have circulated a civil listing priority list with Priority 1 listing work which must be done and which includes injunctions, any applications in cases listed for trial in the next three months, any applications where there is a substantial hearing listed in the next month and all Multi Track hearings where parties agree that it is urgent.
In the Priority 2 list, which consists of hearings which could be done, are enforcement of trading contracts, trial involving the survival of a business or the insolvency of an individual, small and fast track trials where the parties say they are urgent, and appeal in these kinds of cases.
Similarly, in arbitration proceedings, the parties and arbitrators are being encouraged to utilise technology to make sure that hearings take place. We have heard of Zoom being used very successfully for multi-party proceedings.