Should I continue to carry out housing inspections during the coronavirus outbreak?
As the pandemic progresses, more and more people will be forced to self-isolate and, inevitably, both tenants and staff will be affected. Put plans in place to mitigate the impact that this may have, particularly regarding staff shortages. The most important focus here should be communication.
The Covid-19 outbreak will affect the pace of everyday life and delays will be expected. Rather than allowing the pandemic to take over completely, it is important to maintain open communication with tenants as much as possible and inform them of any front-facing challenges that you may face.
The Protocol does envisage that delays may occur and allows for some degree of flexibility. Whilst all efforts should be made to conduct inspections where practical and possible, it should be expected by all parties that timescales will be extended during this crisis. It is fundamental, however, that all changes made to standard practice are communicated and explained to tenants to manage expectations.
Similar flexibility should be afforded to tenants. As households are required to isolate it will not always be possible to gain access to properties as would usually be expected and required. Likewise, vulnerable people will wish to protect themselves and their families and may refuse access on this basis. During this period, a degree of understanding must be exercised and concessions made.
Inspections may be delayed if anyone in the household has symptoms. A questionnaire should be prepared for those visiting properties to assess so far as possible the risk; Personal Protective Equipment should be issued to those visiting, and government guidelines followed.
Related FAQs
An amendment to the Civil Procedure Rules’ Practice Directions has been approved by the Master of the Rolls and the Lord Chancellor on 1 April 2020, and is now Practice Direction 51ZA. This has the effect of allowing the parties to extend by prior written agreement up to a maximum of 56 days (rather than the usual 28 days detailed at CPR 3.8(4)) any rule, practice direction or order provided that any extension does not put at risk any hearing date. This Practice Direction will cease to have effect on 30 October 2020.
Additionally each regions’ Designated Civil Judge (DCJ) has issued a Covid-19 Protocol. There are some minor variations between the regions, but overall the guidance is very similar.
In Northumbria, Durham and Teesside the DCJ guidance for multi-track cases provides that “The parties are at liberty to extend, by consent, any step in the timetable up to a maximum of 90 days (as opposed to the present limit of 28 days)” and the Court does not need to be notified if the Trial date is not effected. Where Trial windows are likely to be impacted due to Covid-19 and the parties are in agreement to extending this, a letter can be sent to the Court with a draft order proposing a new timetable, including a new trial window and agreed availability within the trial window.
The same guidance also confirms that an electronic signature on all documents including witness statements and disclosure statements will suffice.
Yes – there should be a framework in place to ensure that MHFAs are fully supported themselves and so that individuals are supported beyond the support the MHFAs provide.
The workplace will not revert to its pre-Covid-19 state overnight, with social distancing in the work place likely to remain in place for quite some time to come.
This could mean that businesses will need to think carefully about how their capacity will be impacted, and how this will affect their ability to perform contractual obligations.
For example, if a business has an outsourcing contract under which it has to perform a business process, or produce a particular output, will it be able to comply with contractual performance standards whilst social distancing is still in place? In the context of a manufacturing business, what will be the impact on production schedules and delivery dates? There might also be an impact on operating costs, for example if processes are changed and additional shifts are introduced – can these additional costs be sustained?
Businesses need to plan a safe system of work for their employees to ensure they comply with Health and Safety legislation, but they also need to consider how this will impact on their ability to perform pre-existing contractual obligations. Ultimately, contractual arrangements with customers might need to remain on a revised footing for a number of months.
Getting to a point where agreement is reached on allocation of additional costs and/or changes to key elements of a contract such as scope of work, performance standards and delivery date will require co-operation between contracting parties. Again, it is important that any variations that are agreed are recorded properly and follow the required contractual procedures.
Any hearings attended in person will need to be approved by the judge hearing the matter, if necessary, in consultation with the regional lead COP judge. Such requests are highly unlikely to be granted during COVID-19 unless there is a genuine urgency. However, it is deemed to be appropriate matters are likely to be adjourned on the basis that a remote hearing is not possible and a hearing in person is not safe or possible.
- Integration:
- Is the individual held out as being employed by the business by having a company email address, uniform, how would they introduce themselves to customers?
- Exclusivity:
- Is the contractor restricted from working for other organisations without the consent of the end user client?
- Length of engagement:
- Is the contractor engaged to work on a specific project for a defined period? Or are they engaged for an indefinite period with no reference to a specific task or project?
- Pay:
- Are there regular fixed payments or is payment on completion of specific task or commission based? Is the contractor entitled to benefits or bonuses?
- Facilities:
- Does the contractor provide their own equipment and materials to provide the services?
- Financial risk:
- Is the contractor personally responsible for any loss arising from their work in performing the services? Will they have to rectify unsatisfactory work at their own time and expense? Will they have the opportunity to profit from the success of a project?