Other considerations – the mental health and wellbeing of BAME staff and others
Undeniably and understandably BAME staff, as well as those staff who are identified as being at a higher risk, are going to have high levels of stress and anxiety. For some, this may become of such severity that those staff should be considered to be disabled under the Equality Act 2010. The question as to whether someone is disabled is one that should be answered in conjunction with appropriate medical advice. But the question about how to support any staff suffering with stress and anxiety should not be left until that stage. Proactive steps need to be taken and expert advice obtained on what support measures should be put in place. We know that many NHS organisations are already giving the mental wellbeing of their staff the highest priority.
From our perspective, we would ask managers to be mindful that stress and anxiety is likely to feature in how an individual reacts to questions about the level of risk to their health and the impact on their duties. The conversations with some staff may not be easy to have and may be met with challenge.
For those staff who’s stress and anxiety is such that it would qualify as a disability, reasonable adjustments will need to be considered to the processes that you are applying.
An additional point to consider – it might be worth writing to all staff, asking them to come forward if they have any health conditions that they think you ought to be aware of, assuring them that such information is being given in the strictest confidence. You want to make sure that you are taking the appropriate measures to ensure their health and safety.
Related FAQs
The Government announced on 22 June 2020 that it would be making provisions to enable planning permissions that have lapsed since 23 March 2020, and those that are due to lapse before the end of 2020, to be automatically extended.
The Government’s detailed proposals are set out in section 17 of the Business and Planning Act 2020, which entered the statute books on 22 July 2020. If a relevant planning permission is subject to a condition which requires the development to be begun no later than between 19 August 2020 (when section 17 of the Business and Planning Act 2020 will come into effect) and 31 December 2020, the condition is automatically deemed to instead provide that the development must be begun no later than 1 May 2021.
The Act also makes provision for any conditions requiring development to be begun between 23 March 2020 and 19 August 20202 to be extended to 1 May 2021, although this is not automatic. Where the provisions have such retrospective effect, an application is required to the local planning authority. The local planning authority are only able to grant approval, however, if they are satisfied that any EIA and habitats assessments continue to be valid. Deemed approval provisions will apply if the local planning authority do not determine any application within 28 days. The local planning authority are not able to approve such applications after 31 December 2020 so applications should be made in good time in advance of this date. There is the possibility of an appeal against the local planning authority’s decision but notice of the appeal must be submitted before 31 December 2020.
The Act includes similar provisions in relation to both detailed and outline planning permissions.
In the event that the worst happens and contractor insolvency occurs, there are a number of steps which the employer should take immediately:
- Confirm that insolvency has actually occurred and the type of insolvency (for example liquidation or adjudication) – actions taken based on rumours can have adverse consequences
- Secure the site and carry out an audit of the plant, equipment and materials present – this may extend to changing the locks on site in order to prevent overzealous contractors and sub-contractors seeking to return and take what they see as their possessions. The building contract may contain a provision that these are the employer’s property, but they can be difficult to recover if they are not within the employer’s possession – possession is 9/10ths of the law!
- Ensure that there are adequate insurance and health and safety arrangements in place for the site – these would usually be dealt with by the contractor and therefore may no longer be in place, so alternative arrangements may be required
- Ensure that any further payments to the contractor are stopped pending a more detailed review
- Consider whether any off-site materials have already been paid for and can be secured. This can however be difficult in practice where the materials are not physically within the employer’s possession
In addition, there are also a number of further actions which the employer should consider in the slightly longer term:
- Investigate the options available and ascertain the cost of completing the works to assist in deciding how best to proceed
- Consider whether termination of the contractor’s employment under the building contract is required, and if so take the necessary steps in accordance with the building contract
- Consider whether there are any bonds or guarantees in place upon which the employer can rely, and if so assess their terms as to whether and how to make a claim
- Make arrangements to complete the works – as a general rule of thumb the cost of completing the works may increase by around 30% if it is necessary to get a replacement contractor
- Consider whether direct payment to subcontractors is possible or desirable
- Although we would say this(!) we would strongly recommend taking legal advice, as insolvency and its implications are complex and it is easy to inadvertently fall foul of the various different requirements
As mentioned earlier, if an agency is involved you must send them a copy of the status determination statement for each contractor, and they will also have the right to dispute the outcome.
If the agency pays the contractor, they will be responsible for the operation of PAYE and NIC’s deductions and any apprenticeship levy. The agency may try to recover these costs from the end user client.
If workers are supplied by an agency or umbrella company and are already treated as employees by the agency, they will remain unaffected by IR35.
This is likely to be a common situation and employers and employees are going to have to take a pragmatic approach. You could enter into a temporary flexible working arrangement perhaps agreeing to vary working hours/days or reducing targets or agree to use some annual leave.
Employees could ask to take a period of unpaid leave, asserting their right to time off to care for a dependant but the lack of pay is likely to be unappealing.
Alternatively employees who are unable to work because they have caring responsibilities as a result of COVID-19, which includes childcare responsibilities, can be furloughed.
The coronavirus outbreak has seen State support being given to businesses on an unprecedented scale.
This issue is likely to be increasingly relevant as Governments seek to protect and stimulate their economies as they emerge from lockdown.
How have the rules been relaxed in the context of the crisis and what facets of the existing law can be used for the State to provide support to undertakings?